Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
216
matching recommendationsNAICS | 3115 | Dairy Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0621 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,882 | $0 | n/a |
SF0621 # 05 Y:2024 | 05 | 2024 | INSTALL STEAM TRAP | $9,822 | $1,988 | n/a |
SF0621 # 04 Y:2024 | 04 | 2024 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $7,560 | $700 | n/a |
SF0621 # 09 Y:2024 | 09 | 2024 | INSULATE BARE EQUIPMENT | $17,564 | $9,294 | n/a |
SF0621 # 03 Y:2024 | 03 | 2024 | REPAIR OR REPLACE STEAM TRAPS | $6,435 | $478 | n/a |
SF0621 # 08 Y:2024 | 08 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $6,248 | $2,796 | n/a |
SF0621 # 01 Y:2024 | 01 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $12,755 | $300 | n/a |
SF0621 # 11 Y:2024 | 11 | 2024 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $9,426 | $15,810 | n/a |
SF0621 # 07 Y:2024 | 07 | 2024 | USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE | $6,048 | $1,839 | n/a |
SF0621 # 06 Y:2024 | 06 | 2024 | INCREASE AMOUNT OF CONDENSATE RETURNED | $335,892 | $109,275 | n/a |
SF0621 # 12 Y:2024 | 12 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $238,787 | $1,065,639 | n/a |
SF0621 # 10 Y:2024 | 10 | 2024 | INSTALL ISOLATION TRANSFORMER ON ADJUSTABLE FREQUENCY DRIVE | $26,726 | $23,394 | n/a |
SF0619 # 03 Y:2024 | 03 | 2024 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $241 | $0 | n/a |
SF0619 # 01 Y:2024 | 01 | 2024 | REPAIR AND ELIMINATE STEAM LEAKS | $4,612 | $0 | n/a |
SF0619 # 02 Y:2024 | 02 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,589 | $220 | n/a |
SF0619 # 08 Y:2024 | 08 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $6,389 | $4,926 | n/a |
SF0619 # 07 Y:2024 | 07 | 2024 | INSTALL STEAM TRAP | $531,211 | $270,719 | n/a |
SF0619 # 06 Y:2024 | 06 | 2024 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $90,155 | $37,058 | n/a |
SF0619 # 05 Y:2024 | 05 | 2024 | USE MINIMUM STEAM OPERATING PRESSURE | $7,106 | $2,700 | n/a |
SF0619 # 04 Y:2024 | 04 | 2024 | USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE | $39,174 | $7,044 | n/a |
SF0619 # 10 Y:2024 | 10 | 2024 | INSTALL OCCUPANCY SENSORS | $292 | $785 | n/a |
SF0619 # 09 Y:2024 | 09 | 2024 | INSULATE BARE EQUIPMENT | $2,201 | $2,875 | n/a |
SF0619 # 12 Y:2024 | 12 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,993 | $16,268 | n/a |
SF0619 # 11 Y:2024 | 11 | 2024 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $52,391 | $160,125 | n/a |
CI0032 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $47,412 | $313,000 | n/a |