Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
21
matching recommendationsNAICS | 311511 | Fluid Milk Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0160 # 07 Y:2020 | 07 | 2020 | Hire Energy Manager | $50,000 | $2,700 | Not Implemented |
UU0160 # 06 Y:2020 | 06 | 2020 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $960 | $1,140 | Not Implemented |
UU0160 # 05 Y:2020 | 05 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,220 | $23,540 | Implemented |
UU0160 # 04 Y:2020 | 04 | 2020 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $14,460 | $13,100 | Implemented |
UU0160 # 03 Y:2020 | 03 | 2020 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $30,330 | $4,800 | Not Implemented |
UU0160 # 02 Y:2020 | 02 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $41,050 | $179,660 | Implemented |
UU0160 # 01 Y:2020 | 01 | 2020 | INCREASE AMOUNT OF CONDENSATE RETURNED | $47,740 | $212,490 | Implemented |
UU0151 # 04 Y:2019 | 04 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,969 | $1,000 | Not Implemented |
UU0151 # 07 Y:2019 | 07 | 2019 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,760 | $100 | Not Implemented |
UU0151 # 06 Y:2019 | 06 | 2019 | INSTALL OCCUPANCY SENSORS | $1,973 | $7,800 | Not Implemented |
UU0151 # 05 Y:2019 | 05 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,157 | $1,000 | Not Implemented |
UU0151 # 03 Y:2019 | 03 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,711 | $37,970 | Not Implemented |
UU0151 # 02 Y:2019 | 02 | 2019 | OPTIMIZE PLANT POWER FACTOR | $17,315 | $25,000 | Not Implemented |
UU0151 # 01 Y:2019 | 01 | 2019 | OPERATE BOILERS ON HIGH FIRE SETTING | $63,057 | $1,000 | Not Implemented |
UU0131 # 01 Y:2018 | 01 | 2018 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $242,000 | $1,000 | Implemented |
UU0131 # 07 Y:2018 | 07 | 2018 | INSTALL REPLACEMENT DOORS | $4,539 | $300 | Implemented |
UU0131 # 06 Y:2018 | 06 | 2018 | INSULATE BARE EQUIPMENT | $6,501 | $2,665 | Not Implemented |
UU0131 # 05 Y:2018 | 05 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $10,477 | $150 | Implemented |
UU0131 # 04 Y:2018 | 04 | 2018 | INSTALL OCCUPANCY SENSORS | $17,732 | $2,030 | Implemented |
UU0131 # 03 Y:2018 | 03 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $24,471 | $39,272 | Implemented |
UU0131 # 02 Y:2018 | 02 | 2018 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $76,380 | $1,000 | Implemented |