IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,427

matching recommendations
Reset
NAICS 3116 Animal Slaughtering and Processing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UD1012 # 05 Y:2020 05 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $14,521 $1,000 Not Implemented
UD1012 # 06 Y:2020 06 2020 USE EXCESS COLD PROCESS FLUID FOR INDUSTRIAL COOLING NEEDS $67,773 $0 Implemented
UD1012 # 07 Y:2020 07 2020 UTILIZE AN EVAPORATIVE AIR PRE-COOLER OR OTHER HEAT EXCHANGER IN AC SYSTEM $49,540 $21,295 Implemented
UD1012 # 08 Y:2020 08 2020 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $46,434 $0 Not Implemented
UD1012 # 09 Y:2020 09 2020 UTILIZE A LESS EXPENSIVE COOLING METHOD $27,338 $0 Implemented
UD1012 # 10 Y:2020 10 2020 OPTIMIZE PLANT POWER FACTOR $145,150 $100,000 Not Implemented
UD1012 # 11 Y:2020 11 2020 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) $86,219 $9,464 Not Implemented
UD1012 # 12 Y:2020 12 2020 INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS $34,941 $20,000 Not Implemented
UD1012 # 13 Y:2020 13 2020 INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS $17,175 $14,500 Not Implemented
UD1012 # 14 Y:2020 14 2020 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $3,073 $0 Implemented
UD1012 # 15 Y:2020 15 2020 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $1,548 $0 Implemented
UD1012 # 16 Y:2020 16 2020 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $1,160 $0 Implemented
UD1012 # 17 Y:2020 17 2020 USE DIRECT AIR SUPPLY TO EXHAUST HOODS $24,810 $35,000 Implemented
UD1012 # 18 Y:2020 18 2020 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $1,565 $2,500 Not Implemented
UD1008 # 01 Y:2019 01 2019 DEVELOP A REPAIR/REPLACE POLICY $4,386 $0 Implemented
UD1008 # 02 Y:2019 02 2019 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $3,245 $0 Implemented
UD1008 # 03 Y:2019 03 2019 UPGRADE CONTROLS ON COMPRESSORS $10,457 $20,400 Not Implemented
UD1008 # 04 Y:2019 04 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,191 $0 Implemented
UD1008 # 05 Y:2019 05 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,619 $3,650 Implemented
UD1008 # 06 Y:2019 06 2019 USE WASTE HEAT STEAM FOR ABSORPTION REFRIGERATION $8,111 $13,455 Not Implemented
UD1008 # 07 Y:2019 07 2019 USE EXCESS COLD PROCESS FLUID FOR INDUSTRIAL COOLING NEEDS $5,658 $0 Not Implemented
UD1008 # 08 Y:2019 08 2019 USE EXCESS COLD PROCESS FLUID FOR INDUSTRIAL COOLING NEEDS $3,596 $0 Not Implemented
UD1008 # 09 Y:2019 09 2019 USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS $28,777 $27,800 Not Implemented
UD1008 # 10 Y:2019 10 2019 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $6,896 $500 Implemented
UD1008 # 11 Y:2019 11 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,177 $165,000 Implemented