Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
752
matching recommendationsNAICS | 3119 | Other Food Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0125 # 12 Y:2007 | 12 | 2007 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $1,563 | $0 | Implemented |
TA0127 # 01 Y:2006 | 01 | 2006 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $4,212 | $0 | Implemented |
TA0127 # 02 Y:2006 | 02 | 2006 | ELIMINATE LEAKS IN COMBUSTIBLE GAS LINES | $625 | $100 | Implemented |
TA0127 # 04 Y:2006 | 04 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,752 | $0 | Implemented |
CO0593 # 02 Y:2006 | 02 | 2006 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $6,180 | $60 | Implemented |
CO0593 # 03 Y:2006 | 03 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,750 | $120 | Implemented |
CO0593 # 07 Y:2006 | 07 | 2006 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $1,550 | $6,000 | Implemented |
LE0246 # 01 Y:2006 | 01 | 2006 | USE SMALL NUMBER OF HIGH OUTPUT UNITS INSTEAD OF MANY SMALL INEFFICIENT UNITS | $66,327 | $5,000 | Implemented |
LE0246 # 03 Y:2006 | 03 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $9,683 | $6,700 | Implemented |
LE0246 # 05 Y:2006 | 05 | 2006 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $6,033 | $5,000 | Implemented |
LE0246 # 08 Y:2006 | 08 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,948 | $180,000 | Implemented |
LE0246 # 09 Y:2006 | 09 | 2006 | INSTALL OCCUPANCY SENSORS | $1,586 | $450 | Implemented |
LM0117 # 01 Y:2006 | 01 | 2006 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $125,343 | $20,000 | Implemented |
LM0117 # 02 Y:2006 | 02 | 2006 | INSTALL BACK-UP EQUIPMENT | $86,200 | $105,000 | Implemented |
LM0117 # 04 Y:2006 | 04 | 2006 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $15,788 | $3,000 | Implemented |
LM0117 # 06 Y:2006 | 06 | 2006 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,061 | $500 | Implemented |
AM0511 # 01 Y:2006 | 01 | 2006 | OPTIMIZE PLANT POWER FACTOR | $18,600 | $59,000 | Implemented |
AM0511 # 05 Y:2006 | 05 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,160 | $150 | Implemented |
WV0342 # 01 Y:2006 | 01 | 2006 | REPAIR OR REPLACE STEAM TRAPS | $151,419 | $4,500 | Implemented |
WV0342 # 02 Y:2006 | 02 | 2006 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $124,707 | $188,500 | Implemented |
WV0342 # 03 Y:2006 | 03 | 2006 | INCREASE AMOUNT OF CONDENSATE RETURNED | $103,142 | $100,000 | Implemented |
WV0342 # 04 Y:2006 | 04 | 2006 | REDUCE EXCESSIVE BOILER BLOWDOWN | $87,693 | $208,500 | Implemented |
WV0342 # 05 Y:2006 | 05 | 2006 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $76,391 | $42,250 | Implemented |
WV0342 # 07 Y:2006 | 07 | 2006 | OPERATE BOILERS ON HIGH FIRE SETTING | $41,893 | $112,000 | Implemented |
WV0342 # 08 Y:2006 | 08 | 2006 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $26,961 | $1,000 | Implemented |