Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
192
matching recommendationsNAICS | 311911 | Roasted Nuts and Peanut Butter Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0455 # 08 Y:2014 | 08 | 2014 | USE EXCESS COLD PROCESS FLUID FOR INDUSTRIAL COOLING NEEDS | $13,254 | $19,582 | Implemented |
SF0455 # 09 Y:2014 | 09 | 2014 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $13,364 | $21,937 | Implemented |
SF0455 # 10 Y:2014 | 10 | 2014 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,651 | $2,966 | Implemented |
SF0455 # 11 Y:2014 | 11 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $40,078 | $103,067 | Implemented |
SF0455 # 12 Y:2014 | 12 | 2014 | USE STEAM CONDENSATE FOR HOT WATER SUPPLY (NON-POTABLE) | $43,986 | $154,938 | Implemented |
SF0455 # 13 Y:2014 | 13 | 2014 | INSTALL OCCUPANCY SENSORS | $5,163 | $31,786 | Implemented |
SF0455 # 14 Y:2014 | 14 | 2014 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $4,061 | $12,152 | Implemented |
AM0612 # 01 Y:2012 | 01 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,510 | $70 | Not Implemented |
AM0612 # 02 Y:2012 | 02 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,520 | $280 | Implemented |
AM0612 # 03 Y:2012 | 03 | 2012 | INSTALL OCCUPANCY SENSORS | $200 | $0 | Implemented |
NC0444 # 01 Y:2012 | 01 | 2012 | ADJUST BURNERS FOR EFFICIENT OPERATION | $5,257 | $2,000 | Implemented |
NC0444 # 02 Y:2012 | 02 | 2012 | CONVERT COMBUSTION EQUIPMENT TO BURN OIL | $3,445 | $8,500 | Not Implemented |
NC0444 # 03 Y:2012 | 03 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,731 | $500 | Implemented |
NC0444 # 04 Y:2012 | 04 | 2012 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $2,902 | $4,000 | Implemented |
NC0444 # 05 Y:2012 | 05 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,178 | $971 | Implemented |
NC0444 # 06 Y:2012 | 06 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $25,844 | $62,067 | Not Implemented |
NC0444 # 07 Y:2012 | 07 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $22,193 | $53,707 | Not Implemented |
NC0444 # 08 Y:2012 | 08 | 2012 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $6,828 | $32,000 | Not Implemented |
OK0804 # 01 Y:2011 | 01 | 2011 | Install Anaerobic Digester | $544,130 | $5,652,880 | Not Implemented |
OK0804 # 02 Y:2011 | 02 | 2011 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $64,961 | $238,050 | Not Implemented |
OK0804 # 03 Y:2011 | 03 | 2011 | SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS | $12,835 | $19,625 | Not Implemented |
OK0804 # 04 Y:2011 | 04 | 2011 | INSTALL SET-BACK TIMERS | $740 | $1,625 | Not Implemented |
OK0804 # 05 Y:2011 | 05 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,796 | $56,474 | Implemented |
OK0804 # 06 Y:2011 | 06 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,996 | $28,404 | Not Implemented |
OK0804 # 07 Y:2011 | 07 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,223 | $18,797 | Not Implemented |