Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
36
matching recommendationsNAICS | 31212 | Breweries |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0615 # 02 Y:2021 | 02 | 2021 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $540 | $0 | Implemented |
SD0615 # 03 Y:2021 | 03 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $385 | $1,182 | Implemented |
SD0615 # 01 Y:2021 | 01 | 2021 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $4,310 | $6,942 | Implemented |
SD0612 # 06 Y:2021 | 06 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,883 | $2,800 | Not Implemented |
SD0612 # 05 Y:2021 | 05 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,530 | $9,245 | Not Implemented |
SD0612 # 04 Y:2021 | 04 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $957 | $0 | Implemented |
SD0612 # 08 Y:2021 | 08 | 2021 | REPAIR AND ELIMINATE STEAM LEAKS | $557 | $1,000 | Implemented |
SD0612 # 07 Y:2021 | 07 | 2021 | RECOVER WASTE HEAT FROM EQUIPMENT | $14,829 | $44,568 | Not Implemented |
SD0612 # 03 Y:2021 | 03 | 2021 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,826 | $9,545 | Implemented |
SD0612 # 02 Y:2021 | 02 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,879 | $12,356 | Implemented |
SD0612 # 01 Y:2021 | 01 | 2021 | REDESIGN PROCESS | $39,942 | $13,000 | Implemented |
SF0550 # 03 Y:2020 | 03 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,899 | $4,002 | Implemented |
SF0550 # 05 Y:2020 | 05 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,560 | $12,365 | Implemented |
SF0550 # 02 Y:2020 | 02 | 2020 | INSULATE BARE EQUIPMENT | $1,259 | $787 | Implemented |
SF0550 # 04 Y:2020 | 04 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,809 | $17,557 | Implemented |
SF0550 # 01 Y:2020 | 01 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,782 | $1,359 | Implemented |
SD0585 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,052 | $8,453 | Implemented |
SD0585 # 02 Y:2019 | 02 | 2019 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $11,628 | $12,000 | Not Implemented |
SD0585 # 03 Y:2019 | 03 | 2019 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,603 | $200 | Implemented |
SD0585 # 04 Y:2019 | 04 | 2019 | USE PHOTOCELL CONTROLS | $2,188 | $3,520 | Not Implemented |
SD0585 # 05 Y:2019 | 05 | 2019 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $6,928 | $14,000 | Not Implemented |
SD0559 # 04 Y:2018 | 04 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,884 | $14,697 | Not Implemented |
SD0559 # 05 Y:2018 | 05 | 2018 | REDUCE EXCESSIVE BOILER BLOWDOWN | $8,114 | $11,774 | Not Implemented |
SD0559 # 06 Y:2018 | 06 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,587 | $600 | Not Implemented |
SD0559 # 03 Y:2018 | 03 | 2018 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $21,481 | $37,900 | Not Implemented |