Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
25
matching recommendationsNAICS | 312230 | Tobacco Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0230 # 08 Y:2019 | 08 | 2019 | INSTALL TIMERS AND/OR THERMOSTATS | $289 | $20 | Implemented |
TT0230 # 07 Y:2019 | 07 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,661 | $1,618 | Implemented |
TT0230 # 05 Y:2019 | 05 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,238 | $3,200 | Implemented |
TT0230 # 03 Y:2019 | 03 | 2019 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $8,935 | $39,040 | Implemented |
TT0230 # 01 Y:2019 | 01 | 2019 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $37,500 | $0 | Implemented |
TT0218 # 10 Y:2019 | 10 | 2019 | ELIMINATE/REDUCE AN OPERATION | $798 | $340 | Implemented |
TT0218 # 09 Y:2019 | 09 | 2019 | INSULATE BARE EQUIPMENT | $1,202 | $2,400 | Implemented |
TT0218 # 07 Y:2019 | 07 | 2019 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,000 | $2,000 | Implemented |
TT0218 # 06 Y:2019 | 06 | 2019 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $3,670 | $200 | Implemented |
TT0218 # 05 Y:2019 | 05 | 2019 | INCREASE AMOUNT OF CONDENSATE RETURNED | $5,090 | $15,000 | Implemented |
TT0218 # 02 Y:2019 | 02 | 2019 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $21,004 | $2,150 | Implemented |
TT0218 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $21,090 | $85,313 | Implemented |
TT0152 # 08 Y:2015 | 08 | 2015 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $2,434 | $18,270 | Implemented |
TT0152 # 07 Y:2015 | 07 | 2015 | INSTALL OCCUPANCY SENSORS | $2,460 | $10,150 | Implemented |
TT0152 # 05 Y:2015 | 05 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,838 | $1,800 | Implemented |
TT0152 # 03 Y:2015 | 03 | 2015 | UPGRADE CONTROLS ON COMPRESSORS | $6,816 | $2,400 | Implemented |
TT0152 # 02 Y:2015 | 02 | 2015 | UPGRADE CONTROLS ON COMPRESSORS | $8,575 | $15,201 | Implemented |
TT0152 # 01 Y:2015 | 01 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $201,140 | $630,000 | Implemented |
TT0133 # 01 Y:2014 | 01 | 2014 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $37,393 | $0 | Implemented |
TT0133 # 08 Y:2014 | 08 | 2014 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $42,310 | $281,250 | Implemented |
TT0133 # 07 Y:2014 | 07 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $125,381 | $357,200 | Implemented |
TT0133 # 06 Y:2014 | 06 | 2014 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $5,112 | $17,178 | Implemented |
TT0133 # 05 Y:2014 | 05 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,060 | $1,065 | Implemented |
TT0133 # 04 Y:2014 | 04 | 2014 | INSTALL OCCUPANCY SENSORS | $35,591 | $18,500 | Implemented |
TT0133 # 02 Y:2014 | 02 | 2014 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $8,930 | $0 | Implemented |