Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
76
matching recommendationsNAICS | 313210 | Broadwoven Fabric Mills |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0579 # 05 Y:2016 | 05 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,661 | $8,900 | Not Implemented |
NC0579 # 06 Y:2016 | 06 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,575 | $3,000 | Implemented |
NC0579 # 07 Y:2016 | 07 | 2016 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,983 | $4,000 | Not Implemented |
NC0579 # 09 Y:2016 | 09 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,679 | $230 | Not Implemented |
NC0579 # 10 Y:2016 | 10 | 2016 | REPAIR OR REPLACE STEAM TRAPS | $7,750 | $8,500 | Implemented |
NC0579 # 11 Y:2016 | 11 | 2016 | REPAIR AND ELIMINATE STEAM LEAKS | $2,459 | $1,000 | Implemented |
NC0513 # 07 Y:2014 | 07 | 2014 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,117 | $325 | Not Implemented |
NC0513 # 05 Y:2014 | 05 | 2014 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $325 | $175 | Implemented |
NC0513 # 08 Y:2014 | 08 | 2014 | INSTALL OCCUPANCY SENSORS | $3,462 | $3,470 | Implemented |
NC0513 # 09 Y:2014 | 09 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $835 | $240 | Implemented |
NC0513 # 10 Y:2014 | 10 | 2014 | USE PHOTOCELL CONTROLS | $47 | $80 | Not Implemented |
NC0513 # 11 Y:2014 | 11 | 2014 | KEEP BOILER TUBES CLEAN | $48,265 | $15,000 | Implemented |
NC0513 # 12 Y:2014 | 12 | 2014 | REPAIR OR REPLACE STEAM TRAPS | $40,007 | $6,200 | Implemented |
NC0513 # 13 Y:2014 | 13 | 2014 | REPAIR AND ELIMINATE STEAM LEAKS | $20,840 | $20,000 | Implemented |
NC0513 # 14 Y:2014 | 14 | 2014 | INCREASE AMOUNT OF CONDENSATE RETURNED | $9,159 | $5,600 | Not Implemented |
NC0513 # 15 Y:2014 | 15 | 2014 | KEEP BOILER TUBES CLEAN | $13,546 | $500 | Not Implemented |
NC0513 # 16 Y:2014 | 16 | 2014 | INSULATE FEEDWATER TANK | $438 | $257 | Implemented |
NC0513 # 17 Y:2014 | 17 | 2014 | INSTALL / REPAIR INSULATION ON STEAM LINES | $20,435 | $19,607 | Not Implemented |
NC0513 # 18 Y:2014 | 18 | 2014 | RECOVER WASTE HEAT FROM EQUIPMENT | $9,375 | $37,264 | Not Implemented |
NC0513 # 06 Y:2014 | 06 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $34,462 | $24,205 | Not Implemented |
NC0513 # 04 Y:2014 | 04 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,428 | $100 | Implemented |
NC0513 # 03 Y:2014 | 03 | 2014 | UPGRADE CONTROLS ON COMPRESSORS | $21,458 | $10,000 | Implemented |
NC0513 # 02 Y:2014 | 02 | 2014 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $89,082 | $860 | Implemented |
NC0513 # 01 Y:2014 | 01 | 2014 | DEVELOP A REPAIR/REPLACE POLICY | $137,290 | $454,945 | Implemented |
NC0493 # 01 Y:2013 | 01 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $40,789 | $215,791 | Implemented |