Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
44
matching recommendationsNAICS | 3133 | Textile and Fabric Finishing and Fabric Coating Mills |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0889 # 03 Y:2012 | 03 | 2012 | INSULATE BARE EQUIPMENT | $4,743 | $3,920 | Not Implemented |
GT0889 # 02 Y:2012 | 02 | 2012 | REPAIR OR REPLACE STEAM TRAPS | $14,795 | $8,500 | Not Implemented |
GT0889 # 01 Y:2012 | 01 | 2012 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,925 | $1,000 | Not Implemented |
GT0795 # 01 Y:2004 | 01 | 2004 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $43,709 | $0 | Not Implemented |
GT0795 # 10 Y:2004 | 10 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,570 | $2,910 | Not Implemented |
GT0795 # 09 Y:2004 | 09 | 2004 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $18,125 | $6,300 | Not Implemented |
GT0795 # 08 Y:2004 | 08 | 2004 | DISCONNECT BALLASTS | $1,696 | $3,640 | Not Implemented |
GT0795 # 07 Y:2004 | 07 | 2004 | REPAIR AND ELIMINATE STEAM LEAKS | $5,380 | $4,000 | Not Implemented |
GT0795 # 06 Y:2004 | 06 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,890 | $836 | Not Implemented |
GT0795 # 05 Y:2004 | 05 | 2004 | METER WASTE WATER | $7,272 | $0 | Not Implemented |
GT0795 # 04 Y:2004 | 04 | 2004 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $12,828 | $48,861 | Not Implemented |
GT0795 # 03 Y:2004 | 03 | 2004 | USE SYNTHETIC LUBRICANT | $30,353 | $0 | Not Implemented |
GT0795 # 02 Y:2004 | 02 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $42,201 | $34,000 | Not Implemented |
NC0282 # 01 Y:2004 | 01 | 2004 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $99,451 | $151,800 | n/a |
NC0282 # 02 Y:2004 | 02 | 2004 | REDESIGN PROCESS | $5,960 | $6,000 | n/a |
NC0282 # 03 Y:2004 | 03 | 2004 | ADJUST BURNERS FOR EFFICIENT OPERATION | $7,098 | $1,000 | n/a |
NC0282 # 04 Y:2004 | 04 | 2004 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $3,574 | $1,000 | n/a |
NC0282 # 05 Y:2004 | 05 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,233 | $240 | n/a |
NC0282 # 06 Y:2004 | 06 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,215 | $936 | n/a |