Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
43
matching recommendationsNAICS | 315 | Apparel Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0272 # 05 Y:2003 | 05 | 2003 | USE COOLING AIR WHICH COOLS HOT WORK PIECES FOR SPACE HEATING | $351 | $900 | Not Implemented |
NC0272 # 04 Y:2003 | 04 | 2003 | USE PHOTOCELL CONTROLS | $167 | $235 | Implemented |
NC0272 # 02 Y:2003 | 02 | 2003 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,885 | $610 | Implemented |
NC0272 # 01 Y:2003 | 01 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $728 | $2,803 | Implemented |
NC0272 # 03 Y:2003 | 03 | 2003 | RECOVER AND REUSE WASTE MATERIAL | $990 | $400 | Implemented |
NC0264 # 03 Y:2003 | 03 | 2003 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $1,182 | $3,115 | Not Implemented |
NC0264 # 02 Y:2003 | 02 | 2003 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $743 | $3,100 | Not Implemented |
NC0264 # 01 Y:2003 | 01 | 2003 | INSTALL OCCUPANCY SENSORS | $126 | $357 | Not Implemented |
NC0264 # 04 Y:2003 | 04 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $454 | $630 | Implemented |
NC0264 # 05 Y:2003 | 05 | 2003 | RECOVER WASTE HEAT FROM EQUIPMENT | $463 | $800 | Not Implemented |
NC0264 # 08 Y:2003 | 08 | 2003 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $160 | $280 | Not Implemented |
NC0264 # 10 Y:2003 | 10 | 2003 | INSTALL TIMERS AND/OR THERMOSTATS | $1,393 | $350 | Implemented |
NC0264 # 09 Y:2003 | 09 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $264 | $100 | Not Implemented |
NC0264 # 06 Y:2003 | 06 | 2003 | INSULATE BARE EQUIPMENT | $152 | $627 | Implemented |
NC0264 # 07 Y:2003 | 07 | 2003 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $1,875 | $500 | Not Implemented |
AS0361 # 05 Y:2003 | 05 | 2003 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS | $2,290 | $482 | Implemented |
AS0361 # 06 Y:2003 | 06 | 2003 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $2,846 | $1,000 | Not Implemented |
AS0361 # 04 Y:2003 | 04 | 2003 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $11,899 | $17,550 | Not Implemented |
AS0361 # 03 Y:2003 | 03 | 2003 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,305 | $1,400 | Not Implemented |
AS0361 # 02 Y:2003 | 02 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,025 | $30 | Implemented |
AS0361 # 01 Y:2003 | 01 | 2003 | INSTALL / REPAIR INSULATION ON STEAM LINES | $168 | $350 | Implemented |
MA0534 # 06 Y:2003 | 06 | 2003 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $10,591 | $8,425 | Not Implemented |
MA0534 # 05 Y:2003 | 05 | 2003 | INSTALL / REPAIR INSULATION ON STEAM LINES | $19,634 | $12,975 | Not Implemented |
MA0534 # 03 Y:2003 | 03 | 2003 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $27,487 | $53,950 | Not Implemented |
MA0534 # 02 Y:2003 | 02 | 2003 | USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | $76,320 | $57,480 | Not Implemented |