IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

714

matching recommendations
Reset
NAICS 321113 Sawmills
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0602 # 02 Y:2013 02 2013 MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS $17,131 $45,000 Not Implemented
OR0602 # 03 Y:2013 03 2013 UPGRADE CONTROLS ON COMPRESSORS $14,855 $19,467 Implemented
OR0602 # 04 Y:2013 04 2013 INSTALL OCCUPANCY SENSORS $5,434 $10,283 Implemented
OR0602 # 05 Y:2013 05 2013 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT $4,904 $4,472 Not Implemented
OR0602 # 06 Y:2013 06 2013 OPTIMIZE PLANT POWER FACTOR $3,822 $9,150 Implemented
OR0602 # 07 Y:2013 07 2013 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $2,173 $2,020 Not Implemented
OR0602 # 08 Y:2013 08 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,435 $3,004 Implemented
BS0012 # 01 Y:2013 01 2013 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $1,483 $900 Implemented
BS0012 # 02 Y:2013 02 2013 TURN OFF EQUIPMENT WHEN NOT IN USE $3,601 $8,272 Implemented
BS0012 # 03 Y:2013 03 2013 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $5,998 $0 Implemented
BS0012 # 04 Y:2013 04 2013 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $2,065 $8,525 Not Implemented
BS0012 # 05 Y:2013 05 2013 SUBSTITUTE COMPRESSED AIR COOLING WITH WATER OR AIR COOLING $11,249 $3,500 Not Implemented
BS0012 # 06 Y:2013 06 2013 ELIMINATE/REDUCE AN OPERATION $1,098 $422 Not Implemented
BS0012 # 07 Y:2013 07 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,594 $26,100 Implemented
BS0012 # 08 Y:2013 08 2013 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $2,596 $6,725 Not Implemented
BS0012 # 09 Y:2013 09 2013 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $14,916 $14,075 Not Implemented
BS0012 # 10 Y:2013 10 2013 INSULATE BARE EQUIPMENT $340 $2,905 Not Implemented
NC0445 # 01 Y:2012 01 2012 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,196 $0 Implemented
NC0445 # 02 Y:2012 02 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $575 $100 Implemented
NC0445 # 03 Y:2012 03 2012 RECOVER WASTE HEAT FROM EQUIPMENT $1,573 $7,197 Not Implemented
NC0445 # 04 Y:2012 04 2012 USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR $17,271 $73,750 Not Implemented
NC0445 # 05 Y:2012 05 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $336 $126 Implemented
NC0445 # 06 Y:2012 06 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,698 $7,891 Implemented
MS0387 # 01 Y:2012 01 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $12,182 $13,992 Not Implemented
MS0387 # 02 Y:2012 02 2012 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $4,741 $10,125 Not Implemented