Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
273
matching recommendationsNAICS | 32121 | Veneer, Plywood, and Engineered Wood Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0456 # 03 Y:2004 | 03 | 2004 | INSTALL / REPAIR INSULATION ON STEAM LINES | $12,900 | $2,410 | Not Implemented |
OR0456 # 04 Y:2004 | 04 | 2004 | OPTIMIZE PLANT POWER FACTOR | $4,900 | $12,600 | Not Implemented |
OR0456 # 05 Y:2004 | 05 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $11,550 | $15,400 | Implemented |
OR0453 # 01 Y:2004 | 01 | 2004 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $8,340 | $150 | Not Implemented |
OR0453 # 02 Y:2004 | 02 | 2004 | INSTALL / REPAIR INSULATION ON STEAM LINES | $10,100 | $2,950 | Not Implemented |
OR0453 # 03 Y:2004 | 03 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,680 | $6,920 | Not Implemented |
OR0453 # 04 Y:2004 | 04 | 2004 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $113,000 | $84,300 | Not Implemented |
OR0453 # 05 Y:2004 | 05 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $9,300 | $9,460 | Not Implemented |
OR0453 # 06 Y:2004 | 06 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,400 | $6,400 | Not Implemented |
OR0453 # 07 Y:2004 | 07 | 2004 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $11,370 | $1,000 | Not Implemented |
OR0453 # 08 Y:2004 | 08 | 2004 | TURN OFF EQUIPMENT WHEN NOT IN USE | $5,780 | $6,900 | Not Implemented |
OR0453 # 09 Y:2004 | 09 | 2004 | OPTIMIZE PLANT POWER FACTOR | $3,020 | $4,500 | Not Implemented |
OR0447 # 01 Y:2003 | 01 | 2003 | USE FIXTURES TO REDUCE MACHINE CHANGEOUT TIMES | $105,200 | $7,000 | Implemented |
OR0447 # 02 Y:2003 | 02 | 2003 | INSTALL / REPAIR INSULATION ON STEAM LINES | $43,500 | $4,910 | Not Implemented |
OR0447 # 03 Y:2003 | 03 | 2003 | ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS | $28,720 | $150 | Implemented |
OR0447 # 04 Y:2003 | 04 | 2003 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,460 | $880 | Implemented |
OR0430 # 01 Y:2003 | 01 | 2003 | INSTALL AUTOMATIC PACKING EQUIPMENT | $119,450 | $176,200 | Not Implemented |
OR0430 # 02 Y:2003 | 02 | 2003 | MOVE PRODUCT USING MECHANICAL MEANS | $129,340 | $12,250 | Not Implemented |
OR0430 # 03 Y:2003 | 03 | 2003 | INSTALL EQUIPMENT TO MOVE PRODUCT | $11,900 | $9,300 | Not Implemented |
OR0430 # 04 Y:2003 | 04 | 2003 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $30,700 | $17,700 | Implemented |
OR0430 # 05 Y:2003 | 05 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,810 | $9,000 | Implemented |
OR0430 # 06 Y:2003 | 06 | 2003 | UPGRADE CONTROLS ON COMPRESSORS | $11,350 | $2,000 | Implemented |
OR0430 # 07 Y:2003 | 07 | 2003 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $2,950 | $3,100 | Not Implemented |
OR0430 # 08 Y:2003 | 08 | 2003 | INSTALL / REPAIR INSULATION ON STEAM LINES | $8,830 | $14,600 | Implemented |
OR0430 # 09 Y:2003 | 09 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,840 | $1,270 | Implemented |