Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
971
matching recommendationsNAICS | 32191 | Millwork |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0785 # 02 Y:2023 | 02 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $4,224 | $1,583 | Not Implemented |
OR0785 # 03 Y:2023 | 03 | 2023 | OPTIMIZE PLANT POWER FACTOR | $3,141 | $4,510 | Not Implemented |
OR0785 # 04 Y:2023 | 04 | 2023 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $2,475 | $16,140 | Not Implemented |
OR0785 # 05 Y:2023 | 05 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $323 | $0 | Implemented |
OR0785 # 01 Y:2023 | 01 | 2023 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $1,209,151 | $28,500 | Not Implemented |
WV0656 # 09 Y:2023 | 09 | 2023 | OPTIMIZE PLANT POWER FACTOR | $2,669 | $13,005 | Not Implemented |
WV0656 # 11 Y:2023 | 11 | 2023 | DEVELOP A REPAIR/REPLACE POLICY | $1,896 | $8,107 | Implemented |
WV0656 # 10 Y:2023 | 10 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,265 | $1,350 | Implemented |
WV0656 # 13 Y:2023 | 13 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,364 | $3,507 | Implemented |
WV0656 # 08 Y:2023 | 08 | 2023 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,912 | $637 | Implemented |
WV0656 # 12 Y:2023 | 12 | 2023 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $1,376 | $1,500 | Implemented |
WV0656 # 01 Y:2023 | 01 | 2023 | USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS | $114,700 | $500,000 | Not Implemented |
WV0656 # 14 Y:2023 | 14 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,191 | $1,070 | Implemented |
WV0656 # 03 Y:2023 | 03 | 2023 | INSULATE BARE EQUIPMENT | $8,319 | $1,861 | Implemented |
WV0656 # 07 Y:2023 | 07 | 2023 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $2,997 | $1,500 | Implemented |
WV0656 # 04 Y:2023 | 04 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $6,117 | $9,888 | Implemented |
WV0656 # 02 Y:2023 | 02 | 2023 | USE STEAM CONDENSATE FOR HOT WATER SUPPLY (NON-POTABLE) | $17,471 | $75,000 | Not Implemented |
WV0656 # 06 Y:2023 | 06 | 2023 | UPGRADE CONTROLS ON COMPRESSORS | $3,448 | $14,655 | Not Implemented |
WV0656 # 05 Y:2023 | 05 | 2023 | USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER | $4,882 | $17,230 | Not Implemented |
WV0655 # 02 Y:2023 | 02 | 2023 | USE STEAM CONDENSATE FOR HOT WATER SUPPLY (NON-POTABLE) | $39,676 | $165,000 | Not Implemented |
WV0655 # 03 Y:2023 | 03 | 2023 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $12,350 | $1,500 | Implemented |
WV0655 # 01 Y:2023 | 01 | 2023 | USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER | $50,347 | $17,230 | Not Implemented |
WV0655 # 11 Y:2023 | 11 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $324 | $359 | Implemented |
WV0655 # 04 Y:2023 | 04 | 2023 | UPGRADE CONTROLS ON COMPRESSORS | $11,948 | $11,050 | Not Implemented |
WV0655 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,873 | $10,662 | Not Implemented |