Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
464
matching recommendationsNAICS | 32199 | All Other Wood Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UA0203 # 03 Y:2019 | 03 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,238 | $2,765 | Implemented |
UA0203 # 04 Y:2019 | 04 | 2019 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $3,434 | $8,870 | Not Implemented |
UA0203 # 05 Y:2019 | 05 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,053 | $200 | Implemented |
UA0203 # 06 Y:2019 | 06 | 2019 | OPTIMIZE PLANT POWER FACTOR | $3,682 | $2,568 | Implemented |
UA0203 # 07 Y:2019 | 07 | 2019 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $567 | $486 | Implemented |
UU0135 # 01 Y:2018 | 01 | 2018 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $10,541 | $800 | Not Implemented |
UU0135 # 02 Y:2018 | 02 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,170 | $993 | Implemented |
UU0135 # 03 Y:2018 | 03 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,077 | $1,970 | Not Implemented |
UU0135 # 04 Y:2018 | 04 | 2018 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $1,749 | $900 | Implemented |
AM0750 # 08 Y:2018 | 08 | 2018 | PAY UTILITY BILLS ON TIME | $344 | $0 | Implemented |
AM0750 # 07 Y:2018 | 07 | 2018 | USE SYNTHETIC LUBRICANT | $440 | $0 | Not Implemented |
AM0750 # 06 Y:2018 | 06 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $630 | $6 | Implemented |
AM0750 # 05 Y:2018 | 05 | 2018 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $750 | $2,880 | Not Implemented |
AM0750 # 04 Y:2018 | 04 | 2018 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $780 | $0 | Not Implemented |
AM0750 # 03 Y:2018 | 03 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,635 | $4,550 | Implemented |
AM0750 # 02 Y:2018 | 02 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,760 | $1,500 | Implemented |
AM0750 # 01 Y:2018 | 01 | 2018 | OPTIMIZE PLANT POWER FACTOR | $6,550 | $9,100 | Implemented |
OR0699 # 01 Y:2018 | 01 | 2018 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $4,167 | $1,495 | Implemented |
OR0699 # 02 Y:2018 | 02 | 2018 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,077 | $2,087 | Not Implemented |
OR0699 # 03 Y:2018 | 03 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,314 | $3,982 | Implemented |
OR0699 # 04 Y:2018 | 04 | 2018 | UPGRADE CONTROLS ON COMPRESSORS | $6,151 | $23,153 | Implemented |
OR0699 # 05 Y:2018 | 05 | 2018 | USE SOLAR HEAT TO MAKE ELECTRICTY | $592 | $10,650 | Not Implemented |
WV0557 # 01 Y:2018 | 01 | 2018 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $65,760 | $117,200 | Implemented |
WV0557 # 02 Y:2018 | 02 | 2018 | REPAIR AND ELIMINATE STEAM LEAKS | $43,281 | $33,600 | Implemented |
WV0557 # 03 Y:2018 | 03 | 2018 | ADD AREA LIGHTING SWITCHES | $22,313 | $25,000 | Not Implemented |