IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

308

matching recommendations
Reset
NAICS 321999 All Other Miscellaneous Wood Product Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0575 # 05 Y:2011 05 2011 TURN OFF EQUIPMENT WHEN NOT IN USE $8,400 $7,692 Not Implemented
OR0575 # 06 Y:2011 06 2011 REDUCE COMBUSTION AIR FLOW TO OPTIMUM $3,994 $16,460 Not Implemented
OR0575 # 07 Y:2011 07 2011 INSTALL OCCUPANCY SENSORS $4,280 $2,630 Not Implemented
MS0379 # 01 Y:2011 01 2011 RECOVER WASTE HEAT FROM EQUIPMENT $1,001 $3,105 Not Implemented
MS0379 # 02 Y:2011 02 2011 BURN WOOD BY-PRODUCTS FOR HEAT $2,574 $5,626 Not Implemented
MS0374 # 01 Y:2011 01 2011 USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR $57,503 $375,001 Not Implemented
MS0374 # 02 Y:2011 02 2011 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $13,956 $12,825 Implemented
MS0374 # 03 Y:2011 03 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,534 $285 Implemented
MS0374 # 04 Y:2011 04 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,632 $16,560 Implemented
MS0374 # 05 Y:2011 05 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,392 $10,340 Implemented
MS0374 # 06 Y:2011 06 2011 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $1,329 $771 Not Implemented
MS0374 # 07 Y:2011 07 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,023 $7,463 Implemented
UD0810 # 01 Y:2010 01 2010 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $27,208 $1,500 Implemented
UD0810 # 02 Y:2010 02 2010 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $9,919 $1,000 Implemented
UD0810 # 03 Y:2010 03 2010 OPTIMIZE PLANT POWER FACTOR $5,338 $32,000 Not Implemented
UD0810 # 04 Y:2010 04 2010 USE RADIANT HEATER FOR SPOT HEATING $5,042 $2,000 Not Implemented
UD0810 # 05 Y:2010 05 2010 METER WASTE WATER $4,167 $1,500 Not Implemented
UD0810 # 06 Y:2010 06 2010 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,405 $2,242 Implemented
UD0810 # 07 Y:2010 07 2010 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,614 $1,000 Implemented
UD0810 # 08 Y:2010 08 2010 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,568 $0 Implemented
UD0810 # 09 Y:2010 09 2010 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $944 $1,834 Implemented
UD0810 # 10 Y:2010 10 2010 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $532 $740 Not Implemented
UD0810 # 11 Y:2010 11 2010 INSTALL OCCUPANCY SENSORS $347 $34 Not Implemented
UD0810 # 12 Y:2010 12 2010 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $200 $500 Not Implemented
SF0380 # 01 Y:2010 01 2010 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,300 $360 Implemented