Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
21
matching recommendationsNAICS | 322130 | Paperboard Mills |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NT0029 # 05 Y:2024 | 05 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,550 | $21,900 | n/a |
NT0029 # 04 Y:2024 | 04 | 2024 | APPLY FOR INVESTMENT INCENTIVES | $204,971 | $10,000 | n/a |
NT0029 # 03 Y:2024 | 03 | 2024 | OPTIMIZE PLANT POWER FACTOR | $34,386 | $117,351 | n/a |
NT0029 # 02 Y:2024 | 02 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,227 | $1,819 | n/a |
NT0029 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,179 | $5,609 | n/a |
AM0787 # 03 Y:2019 | 03 | 2019 | REPAIR OR REPLACE STEAM TRAPS | $56,595 | $10,440 | Implemented |
AM0787 # 08 Y:2019 | 08 | 2019 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $399 | $280 | Not Implemented |
AM0787 # 07 Y:2019 | 07 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,577 | $2,640 | Implemented |
AM0787 # 06 Y:2019 | 06 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,322 | $825 | Implemented |
AM0787 # 05 Y:2019 | 05 | 2019 | OPTIMIZE PLANT POWER FACTOR | $70,814 | $178,864 | Implemented |
AM0787 # 04 Y:2019 | 04 | 2019 | USE SYNTHETIC LUBRICANT | $13,271 | $14,560 | Implemented |
AM0787 # 02 Y:2019 | 02 | 2019 | USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST | $312,044 | $849,614 | Not Implemented |
AM0787 # 01 Y:2019 | 01 | 2019 | USE STEAM PRESSURE REDUCTION TO GENERATE POWER | $290,927 | $1,011,274 | Not Implemented |
AM0487 # 01 Y:2005 | 01 | 2005 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $108,000 | $24,500 | Not Implemented |
AM0487 # 08 Y:2005 | 08 | 2005 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $8,940 | $4,200 | Not Implemented |
AM0487 # 07 Y:2005 | 07 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $920 | $500 | Not Implemented |
AM0487 # 06 Y:2005 | 06 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,700 | $2,100 | Not Implemented |
AM0487 # 05 Y:2005 | 05 | 2005 | USE PHOTOCELL CONTROLS | $2,600 | $100 | Not Implemented |
AM0487 # 04 Y:2005 | 04 | 2005 | INSTALL OCCUPANCY SENSORS | $10,400 | $1,200 | Not Implemented |
AM0487 # 03 Y:2005 | 03 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,460 | $500 | Not Implemented |
AM0487 # 02 Y:2005 | 02 | 2005 | OPTIMIZE PLANT POWER FACTOR | $27,000 | $61,600 | Not Implemented |