Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
29
matching recommendationsNAICS | 32221 | Paperboard Container Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0360 # 05 Y:2007 | 05 | 2007 | DEVELOP A REPAIR/REPLACE POLICY | $1,032 | $662 | Not Implemented |
NC0360 # 04 Y:2007 | 04 | 2007 | TURN OFF EQUIPMENT WHEN NOT IN USE | $12,267 | $0 | Implemented |
NC0360 # 08 Y:2007 | 08 | 2007 | USE PHOTOCELL CONTROLS | $761 | $750 | Implemented |
NC0360 # 03 Y:2007 | 03 | 2007 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $35,946 | $33,785 | Not Implemented |
NC0360 # 02 Y:2007 | 02 | 2007 | REPAIR AND ELIMINATE STEAM LEAKS | $9,594 | $2,250 | Implemented |
NC0360 # 07 Y:2007 | 07 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $836 | $300 | Implemented |
NC0360 # 06 Y:2007 | 06 | 2007 | RECOVER WASTE HEAT FROM EQUIPMENT | $12,731 | $12,000 | Implemented |
NC0360 # 01 Y:2007 | 01 | 2007 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $20,317 | $10,000 | Implemented |
NC0340 # 06 Y:2006 | 06 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,146 | $1,700 | Not Implemented |
NC0340 # 13 Y:2006 | 13 | 2006 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $61,400 | $25,000 | Not Implemented |
NC0340 # 12 Y:2006 | 12 | 2006 | OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES | $18,650 | $20,000 | Not Implemented |
NC0340 # 11 Y:2006 | 11 | 2006 | OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES | $20,000 | $20,000 | Implemented |
NC0340 # 10 Y:2006 | 10 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,390 | $50 | Implemented |
NC0340 # 09 Y:2006 | 09 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $129 | $377 | Not Implemented |
NC0340 # 08 Y:2006 | 08 | 2006 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $272 | $500 | Implemented |
NC0340 # 07 Y:2006 | 07 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,998 | $0 | Implemented |
NC0340 # 05 Y:2006 | 05 | 2006 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,698 | $7,600 | Not Implemented |
NC0340 # 04 Y:2006 | 04 | 2006 | INSULATE FEEDWATER TANK | $879 | $220 | Implemented |
NC0340 # 03 Y:2006 | 03 | 2006 | REPAIR OR REPLACE STEAM TRAPS | $4,704 | $1,500 | Implemented |
NC0340 # 02 Y:2006 | 02 | 2006 | CLOSE OFF UNNEEDED STEAM LINES | $13,322 | $0 | Implemented |
NC0340 # 01 Y:2006 | 01 | 2006 | ADJUST BURNERS FOR EFFICIENT OPERATION | $1,720 | $1,800 | Implemented |
NC0322 # 01 Y:2005 | 01 | 2005 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $139,400 | $9,500 | Implemented |
NC0322 # 06 Y:2005 | 06 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $462 | $100 | Implemented |
NC0322 # 05 Y:2005 | 05 | 2005 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $2,592 | $821 | Implemented |
NC0322 # 03 Y:2005 | 03 | 2005 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $74,009 | $100,000 | Not Implemented |