Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
143
matching recommendationsNAICS | 322212 | Folding Paperboard Box Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0438 # 05 Y:2013 | 05 | 2013 | INTERLOCK HEATING AND AIR CONDITIONING SYSTEMS TO PREVENT SIMULTANEOUS OPERATION | $3,906 | $4,995 | Implemented |
SF0438 # 06 Y:2013 | 06 | 2013 | INTERLOCK HEATING AND AIR CONDITIONING SYSTEMS TO PREVENT SIMULTANEOUS OPERATION | $4,153 | $5,267 | Implemented |
MZ0122 # 01 Y:2013 | 01 | 2013 | INSULATE BARE EQUIPMENT | $21,142 | $3,276 | Implemented |
MZ0122 # 03 Y:2013 | 03 | 2013 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $3,627 | $1,000 | Implemented |
MZ0122 # 04 Y:2013 | 04 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,176 | $4,981 | Implemented |
MZ0122 # 05 Y:2013 | 05 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,872 | $1,308 | Implemented |
MZ0122 # 06 Y:2013 | 06 | 2013 | INSTALL OCCUPANCY SENSORS | $1,742 | $1,240 | Implemented |
MZ0122 # 07 Y:2013 | 07 | 2013 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,732 | $281 | Implemented |
MZ0122 # 09 Y:2013 | 09 | 2013 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $576 | $500 | Implemented |
NC0486 # 01 Y:2013 | 01 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,365 | $4,000 | Implemented |
NC0486 # 02 Y:2013 | 02 | 2013 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $150 | $25 | Implemented |
SU0326 # 01 Y:2012 | 01 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,463 | $0 | Implemented |
SU0326 # 02 Y:2012 | 02 | 2012 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $8,393 | $2,291 | Implemented |
SU0326 # 03 Y:2012 | 03 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $148 | $59 | Implemented |
SU0326 # 07 Y:2012 | 07 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,280 | $3,077 | Implemented |
SU0326 # 09 Y:2012 | 09 | 2012 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $61,559 | $262,789 | Implemented |
OK0810 # 02 Y:2011 | 02 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $44,840 | $11,400 | Implemented |
OK0810 # 04 Y:2011 | 04 | 2011 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $5,317 | $0 | Implemented |
NC0425 # 01 Y:2011 | 01 | 2011 | TURN OFF EQUIPMENT WHEN NOT IN USE | $14,162 | $5,000 | Implemented |
NC0425 # 04 Y:2011 | 04 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $347 | $100 | Implemented |
NC0425 # 08 Y:2011 | 08 | 2011 | INSTALL OCCUPANCY SENSORS | $630 | $980 | Implemented |
NC0425 # 09 Y:2011 | 09 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,465 | $3,975 | Implemented |
NC0425 # 10 Y:2011 | 10 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $20,987 | $71,380 | Implemented |
OK0808 # 02 Y:2011 | 02 | 2011 | USE POWER DURING OFF-PEAK PERIODS | $19,801 | $226 | Implemented |
OK0808 # 03 Y:2011 | 03 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,547 | $17,879 | Implemented |