Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
63
matching recommendationsNAICS | 32222 | Paper Bag and Coated and Treated Paper Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BD0459 # 11 Y:2015 | 11 | 2015 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $3,826 | $18 | Implemented |
BD0459 # 10 Y:2015 | 10 | 2015 | USE RADIANT HEATER FOR SPOT HEATING | $1,263 | $3,500 | Implemented |
BD0459 # 09 Y:2015 | 09 | 2015 | LOWER COMPRESSOR PRESSURE THROUGH A/C SYSTEM MODIFICATION | $142 | $20 | Implemented |
BD0459 # 08 Y:2015 | 08 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $377 | $800 | Implemented |
BD0459 # 07 Y:2015 | 07 | 2015 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $7,002 | $30,399 | Implemented |
BD0459 # 06 Y:2015 | 06 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,004 | $300 | Implemented |
BD0459 # 01 Y:2015 | 01 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $19,318 | $10,000 | Implemented |
BD0459 # 02 Y:2015 | 02 | 2015 | INSTALL OCCUPANCY SENSORS | $1,792 | $1,350 | Implemented |
BD0459 # 03 Y:2015 | 03 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $256 | $300 | Implemented |
BD0459 # 04 Y:2015 | 04 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $392 | $1,300 | Implemented |
BD0459 # 05 Y:2015 | 05 | 2015 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,648 | $2,700 | Implemented |
BD0432 # 02 Y:2013 | 02 | 2013 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $6,185 | $16,000 | Not Implemented |
BD0432 # 07 Y:2013 | 07 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $378 | $20 | Not Implemented |
BD0432 # 06 Y:2013 | 06 | 2013 | SHUT OFF PILOTS IN STANDBY EQUIPMENT | $212 | $40 | Not Implemented |
BD0432 # 05 Y:2013 | 05 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $793 | $2,777 | Not Implemented |
BD0432 # 04 Y:2013 | 04 | 2013 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,312 | $500 | Not Implemented |
BD0432 # 01 Y:2013 | 01 | 2013 | USE RADIANT HEATER FOR SPOT HEATING | $9,498 | $14,512 | Not Implemented |
BD0432 # 03 Y:2013 | 03 | 2013 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,832 | $4,800 | Not Implemented |
BD0391 # 01 Y:2011 | 01 | 2011 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $29,184 | $2,500 | Implemented |
BD0391 # 05 Y:2011 | 05 | 2011 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,045 | $1,500 | Not Implemented |
BD0391 # 02 Y:2011 | 02 | 2011 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $15,276 | $7,000 | Not Implemented |
BD0391 # 04 Y:2011 | 04 | 2011 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,808 | $11,500 | Implemented |
BD0391 # 06 Y:2011 | 06 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $738 | $1,000 | Implemented |
BD0391 # 03 Y:2011 | 03 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,439 | $7,923 | Implemented |
BD0376 # 07 Y:2010 | 07 | 2010 | USE RADIANT HEATER FOR SPOT HEATING | $7,210 | $9,000 | Not Implemented |