IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

83

matching recommendations
Reset
NAICS 324 Petroleum and Coal Products Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UF0605 # 04 Y:2023 04 2023 IMPROVE COMBUSTION CONTROL CAPABILITY $3,043 $2,800 Implemented
UF0605 # 03 Y:2023 03 2023 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $13,825 $11,200 Implemented
UF0605 # 05 Y:2023 05 2023 LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS $1,444,605 $0 Implemented
UF0605 # 01 Y:2023 01 2023 USE SOLAR HEAT TO MAKE ELECTRICTY $108,422 $322,608 Not Implemented
UF0605 # 02 Y:2023 02 2023 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $38,052 $10,000 Implemented
UF0605 # 06 Y:2023 06 2023 LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT $5,654 $20,000 Implemented
UF0523 # 09 Y:2019 09 2019 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $735 $0 Not Implemented
UF0523 # 02 Y:2019 02 2019 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $19,621 $2,800 Not Implemented
UF0523 # 08 Y:2019 08 2019 TURN OFF EQUIPMENT WHEN NOT IN USE $1,990 $0 Not Implemented
UF0523 # 07 Y:2019 07 2019 INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN $2,600 $9,464 Not Implemented
UF0523 # 04 Y:2019 04 2019 REPAIR AND ELIMINATE STEAM LEAKS $14,533 $1,600 Implemented
UF0523 # 03 Y:2019 03 2019 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $14,666 $30,000 Not Implemented
UF0523 # 01 Y:2019 01 2019 REDUCE DELIVERY SCHEDULES $43,506 $0 Not Implemented
UF0523 # 05 Y:2019 05 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,991 $4,959 Implemented
UF0523 # 06 Y:2019 06 2019 INSTALL / REPAIR INSULATION ON STEAM LINES $2,925 $1,308 Implemented
MI0249 # 06 Y:2013 06 2013 MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT $2,451 $347 Implemented
MI0249 # 01 Y:2013 01 2013 CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS $1,845,922 $2,000,000 Implemented
MI0249 # 02 Y:2013 02 2013 INSULATE BARE EQUIPMENT $38,483 $20,790 Not Implemented
MI0249 # 08 Y:2013 08 2013 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,904 $80 Implemented
MI0249 # 04 Y:2013 04 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $8,076 $13,090 Not Implemented
MI0249 # 09 Y:2013 09 2013 INSTALL / REPAIR INSULATION ON STEAM LINES $329 $1,104 Not Implemented
MI0249 # 03 Y:2013 03 2013 INCREASE EFFICIENCY OF TRUCKS $14,224 $11,600 Implemented
MI0249 # 07 Y:2013 07 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,546 $1,660 Implemented
MI0249 # 05 Y:2013 05 2013 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $5,223 $2,520 Implemented
MI0247 # 08 Y:2013 08 2013 MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT $870 $347 Implemented