IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

300

matching recommendations
Reset
NAICS 324122 Asphalt Shingle and Coating Materials Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
DL0136 # 03 Y:2014 03 2014 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,610 $1,020 Not Implemented
DL0136 # 02 Y:2014 02 2014 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $11,940 $11,600 Implemented
DL0136 # 01 Y:2014 01 2014 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $60,975 $50,000 Implemented
DL0136 # 04 Y:2014 04 2014 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $4,030 $20,000 Implemented
DL0136 # 05 Y:2014 05 2014 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $5,590 $0 Implemented
DL0136 # 06 Y:2014 06 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,190 $6,400 Not Implemented
UD0897 # 04 Y:2014 04 2014 TURN OFF EQUIPMENT WHEN NOT IN USE $2,897 $5,000 Not Implemented
UD0897 # 09 Y:2014 09 2014 USE RADIANT HEATER FOR SPOT HEATING $22,517 $48,000 Not Implemented
UD0897 # 08 Y:2014 08 2014 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $142 $900 Not Implemented
UD0897 # 07 Y:2014 07 2014 ADD AREA LIGHTING SWITCHES $664 $600 Not Implemented
UD0897 # 06 Y:2014 06 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,409 $5,020 Not Implemented
UD0897 # 05 Y:2014 05 2014 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $765 $0 Implemented
UD0897 # 01 Y:2014 01 2014 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $10,780 $0 Not Implemented
UD0897 # 02 Y:2014 02 2014 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $405 $0 Not Implemented
UD0897 # 03 Y:2014 03 2014 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $755 $1,000 Implemented
SF0433 # 01 Y:2013 01 2013 INSTALL SPECTRAL REFLECTORS / DELAMP $1,312 $393 Implemented
SF0433 # 02 Y:2013 02 2013 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $3,790 $3,152 Implemented
SF0433 # 03 Y:2013 03 2013 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $10,785 $9,062 Not Implemented
SF0433 # 07 Y:2013 07 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,866 $32,002 Not Implemented
SF0433 # 06 Y:2013 06 2013 USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS $9,806 $46,860 Implemented
SF0433 # 05 Y:2013 05 2013 INSTALL OCCUPANCY SENSORS $7,030 $21,402 Implemented
SF0433 # 04 Y:2013 04 2013 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $4,718 $11,431 Not Implemented
SD0453 # 01 Y:2012 01 2012 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $19,250 $200 Implemented
SD0453 # 02 Y:2012 02 2012 TURN OFF EQUIPMENT WHEN NOT IN USE $11,500 $200 Implemented
SD0453 # 03 Y:2012 03 2012 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $5,950 $200 Implemented