Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
376
matching recommendationsNAICS | 325 | Chemical Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0672 # 08 Y:2025 | 08 | 2025 | RECOVER WASTE HEAT FROM EQUIPMENT | $21,315 | $2,000 | n/a |
SD0672 # 04 Y:2025 | 04 | 2025 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,349 | $0 | n/a |
SD0672 # 02 Y:2025 | 02 | 2025 | USE BATTERY STORAGE FOR DEMAND CONTROL | $11,678 | $2,631 | n/a |
SD0665 # 05 Y:2025 | 05 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,342 | $2,233 | n/a |
SD0665 # 01 Y:2025 | 01 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $614,791 | $395,505 | n/a |
SD0665 # 03 Y:2025 | 03 | 2025 | ADOPT IN-HOUSE MATERIAL GENERATION | $23,739 | $46,406 | n/a |
SD0665 # 06 Y:2025 | 06 | 2025 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $74,386 | $209,425 | n/a |
SD0665 # 04 Y:2025 | 04 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $58,983 | $101,750 | n/a |
SD0665 # 02 Y:2025 | 02 | 2025 | USE BATTERY STORAGE FOR DEMAND CONTROL | $203,574 | $5,892 | n/a |
SF0629 # 03 Y:2025 | 03 | 2025 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,560 | $254 | n/a |
SF0629 # 01 Y:2025 | 01 | 2025 | TURN OFF EQUIPMENT WHEN NOT IN USE | $3,502 | $0 | n/a |
SF0629 # 06 Y:2025 | 06 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,343 | $22,807 | n/a |
SF0629 # 04 Y:2025 | 04 | 2025 | INSULATE BARE EQUIPMENT | $6,353 | $4,013 | n/a |
SF0629 # 02 Y:2025 | 02 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $942 | $0 | n/a |
SF0629 # 05 Y:2025 | 05 | 2025 | INSTALL OCCUPANCY SENSORS | $2,585 | $8,372 | n/a |
SF0629 # 07 Y:2025 | 07 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $121,562 | $882,352 | n/a |
SF0628 # 02 Y:2025 | 02 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,482 | $770 | n/a |
SF0628 # 03 Y:2025 | 03 | 2025 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $1,061 | $6,460 | n/a |
SF0628 # 01 Y:2025 | 01 | 2025 | TURN OFF EQUIPMENT WHEN NOT IN USE | $72,544 | $0 | n/a |
SD0661 # 06 Y:2024 | 06 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $2,354 | $0 | Implemented |
SD0661 # 13 Y:2024 | 13 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,043 | $19,842 | Implemented |
SD0661 # 07 Y:2024 | 07 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $854 | $250 | Implemented |
SD0661 # 04 Y:2024 | 04 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $3,584 | $4,191 | Not Implemented |
SD0661 # 03 Y:2024 | 03 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,348 | $676 | Implemented |
SD0661 # 08 Y:2024 | 08 | 2024 | ADOPT IN-HOUSE MATERIAL GENERATION | $809,075 | $47,546 | Not Implemented |