IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

5,503

matching recommendations
Reset
NAICS 325 Chemical Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK1046 # 01 Y:2021 01 2021 RECOVER WASTE HEAT FROM EQUIPMENT $2,296 $2,422 Not Implemented
OK1046 # 02 Y:2021 02 2021 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $827 $0 Implemented
OK1046 # 03 Y:2021 03 2021 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $569 $512 Not Implemented
OK1046 # 04 Y:2021 04 2021 OPTIMIZE PLANT POWER FACTOR $2,125 $8,240 Not Implemented
OK1046 # 05 Y:2021 05 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $16,027 $38,688 Implemented
UD1027 # 01 Y:2021 01 2021 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,612 $0 Implemented
UD1027 # 02 Y:2021 02 2021 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) $11,486 $1,000 Not Implemented
UD1027 # 03 Y:2021 03 2021 RECOVER AND REUSE COOLING WATER $7,993 $0 Not Implemented
UD1027 # 04 Y:2021 04 2021 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $2,522 $0 Not Implemented
UD1027 # 05 Y:2021 05 2021 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,842 $1,000 Implemented
UD1027 # 06 Y:2021 06 2021 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $1,443 $0 Not Implemented
UD1027 # 07 Y:2021 07 2021 REPAIR OR REPLACE STEAM TRAPS $6,067 $4,875 Not Implemented
UD1027 # 08 Y:2021 08 2021 AVOID COOLING OF PROCESS STREAMS OR MATERIALS THAT MUST SUBSEQUENTLY BE HEATED $2,481 $4,300 Not Implemented
UD1027 # 09 Y:2021 09 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $17,013 $65,250 Implemented
UD1027 # 10 Y:2021 10 2021 INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS $10,735 $43,000 Not Implemented
MI0383 # 01 Y:2020 01 2020 USE SOLAR HEAT TO HEAT WATER $10,293 $12,280 Implemented
MI0383 # 02 Y:2020 02 2020 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $9,548 $480 Not Implemented
MI0383 # 03 Y:2020 03 2020 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $2,976 $1,428 Implemented
MI0383 # 04 Y:2020 04 2020 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) $2,698 $1,306 Implemented
MI0383 # 05 Y:2020 05 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,327 $2,436 Implemented
MI0383 # 06 Y:2020 06 2020 INSTALL OCCUPANCY SENSORS $552 $882 Implemented
UF0558 # 01 Y:2020 01 2020 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $20,597 $19,045 Implemented
UF0558 # 02 Y:2020 02 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,420 $456 Implemented
UF0558 # 03 Y:2020 03 2020 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $42,983 $7,127 Implemented
UF0558 # 04 Y:2020 04 2020 USE FILTRATION, CENTRIFUGING TO REMOVE CONTAMINANTS $1,517,489 $143,275 Implemented