Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
106
matching recommendationsNAICS | 325 | Chemical Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UM0306 # 02 Y:2006 | 02 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $11,812 | $22,458 | Not Implemented |
UM0306 # 03 Y:2006 | 03 | 2006 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $9,934 | $2,500 | Not Implemented |
UM0306 # 04 Y:2006 | 04 | 2006 | ELIMINATE COOLING OF PROCESS STREAMS WHICH SUBSEQUENTLY MUST BE HEATED AND VICE VERSA | $8,336 | $7,520 | Implemented |
UM0306 # 05 Y:2006 | 05 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,571 | $9,421 | Implemented |
UM0306 # 06 Y:2006 | 06 | 2006 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $2,482 | $2,429 | Not Implemented |
UM0306 # 07 Y:2006 | 07 | 2006 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,558 | $197 | Implemented |
UM0261 # 01 Y:2004 | 01 | 2004 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $96,676 | $11,096 | Not Implemented |
UM0261 # 02 Y:2004 | 02 | 2004 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $16,377 | $47,700 | Not Implemented |
UM0261 # 03 Y:2004 | 03 | 2004 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $7,493 | $2,000 | Implemented |
UM0261 # 04 Y:2004 | 04 | 2004 | INSULATE BARE EQUIPMENT | $6,503 | $500 | Implemented |
UM0261 # 05 Y:2004 | 05 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,770 | $1,711 | Implemented |
UM0261 # 06 Y:2004 | 06 | 2004 | COVER OPEN TANKS | $625 | $300 | Implemented |
UM0254 # 01 Y:2004 | 01 | 2004 | ADOPT IN-HOUSE MATERIAL GENERATION | $31,255 | $30,000 | Not Implemented |
UM0254 # 02 Y:2004 | 02 | 2004 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $9,650 | $2,200 | Implemented |
UM0254 # 03 Y:2004 | 03 | 2004 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $6,907 | $0 | Implemented |
UM0254 # 04 Y:2004 | 04 | 2004 | USE WASTE HEAT FROM FLUE GASES TO HEAT SPACE CONDITIONING AIR | $3,584 | $15,000 | Not Implemented |
UM0254 # 05 Y:2004 | 05 | 2004 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $3,267 | $10,000 | Not Implemented |
UM0254 # 06 Y:2004 | 06 | 2004 | INSTALL / REPAIR INSULATION ON STEAM LINES | $3,010 | $1,080 | Implemented |
UM0254 # 07 Y:2004 | 07 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,479 | $1,038 | Implemented |
UM0244 # 01 Y:2003 | 01 | 2003 | ADOPT IN-HOUSE MATERIAL GENERATION | $101,745 | $30,000 | Not Implemented |
UM0244 # 02 Y:2003 | 02 | 2003 | SIZE TRUCKS TO JOB | $76,800 | $54,000 | Implemented |
UM0244 # 03 Y:2003 | 03 | 2003 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $582 | $2,477 | Not Implemented |
UM0244 # 04 Y:2003 | 04 | 2003 | SHIFT FROM DAYTIME TO NIGHTTIME OPERATION | $26,499 | $51,860 | Not Implemented |
UM0244 # 05 Y:2003 | 05 | 2003 | INSULATE BARE EQUIPMENT | $2,023 | $521 | Implemented |
UM0244 # 06 Y:2003 | 06 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,934 | $13,221 | Not Implemented |