IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

126

matching recommendations
Reset
NAICS 325 Chemical Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
MS0406 # 03 Y:2022 03 2022 TURN OFF EQUIPMENT WHEN NOT IN USE $5,220 $0 Implemented
MS0406 # 02 Y:2022 02 2022 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,570 $0 Not Implemented
MS0406 # 01 Y:2022 01 2022 REPLACE BOILER $17,347 $165,000 Not Implemented
TT0187 # 03 Y:2017 03 2017 UPGRADE CONTROLS ON COMPRESSORS $24,005 $30,000 Implemented
TT0187 # 09 Y:2017 09 2017 UPGRADE CONTROLS ON COMPRESSORS $1,046 $3,200 Not Implemented
TT0187 # 02 Y:2017 02 2017 INCREASE AMOUNT OF CONDENSATE RETURNED $52,000 $14,250 Implemented
TT0187 # 06 Y:2017 06 2017 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $6,126 $2,000 Not Implemented
TT0187 # 08 Y:2017 08 2017 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,556 $0 Implemented
TT0187 # 07 Y:2017 07 2017 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY $2,097 $1,000 Not Implemented
TT0187 # 05 Y:2017 05 2017 MINIMIZE BOILER BLOWDOWN WITH BETTER FEEDWATER TREATMENT $8,095 $1,311 Implemented
TT0187 # 04 Y:2017 04 2017 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $19,000 $3,000 Implemented
TT0187 # 01 Y:2017 01 2017 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $77,734 $24,500 Not Implemented
UA0096 # 01 Y:2013 01 2013 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $13,079 $0 Implemented
UA0096 # 08 Y:2013 08 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $321 $1,000 Not Implemented
UA0096 # 06 Y:2013 06 2013 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $766 $8 Not Implemented
UA0096 # 07 Y:2013 07 2013 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $485 $400 Not Implemented
UA0096 # 05 Y:2013 05 2013 INSTALL TIMERS AND/OR THERMOSTATS $3,456 $1,320 Implemented
UA0096 # 04 Y:2013 04 2013 INSTALL OCCUPANCY SENSORS $1,997 $545 Implemented
UA0096 # 02 Y:2013 02 2013 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $817 $996 Implemented
UA0096 # 03 Y:2013 03 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $12,715 $39,573 Implemented
MS0371 # 07 Y:2011 07 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,774 $19,214 Not Implemented
MS0371 # 02 Y:2011 02 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,866 $2,431 Not Implemented
MS0371 # 06 Y:2011 06 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,056 $11,255 Not Implemented
MS0371 # 04 Y:2011 04 2011 INCREASE AMOUNT OF CONDENSATE RETURNED $7,004 $11,785 Not Implemented
MS0371 # 03 Y:2011 03 2011 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY $5,839 $8,380 Not Implemented