matching recommendationsNAICS | 3251 | Basic Chemical Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0111 # 07 Y:2006 | 07 | 2006 | USE MINIMUM STEAM OPERATING PRESSURE | $22,776 | $0 | Implemented |
IC0111 # 12 Y:2006 | 12 | 2006 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $45,671 | $195,432 | Implemented |
IC0111 # 11 Y:2006 | 11 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $23,163 | $1,600 | Implemented |
IC0111 # 09 Y:2006 | 09 | 2006 | REPAIR OR REPLACE STEAM TRAPS | $158,427 | $5,152 | Implemented |
IC0111 # 08 Y:2006 | 08 | 2006 | REPAIR AND ELIMINATE STEAM LEAKS | $9,304 | $2,800 | Implemented |
IC0111 # 06 Y:2006 | 06 | 2006 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $57,000 | $36,000 | Not Implemented |
IC0111 # 05 Y:2006 | 05 | 2006 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $11,047 | $30,000 | Not Implemented |
IC0111 # 04 Y:2006 | 04 | 2006 | INCREASE AMOUNT OF CONDENSATE RETURNED | $93,000 | $235,998 | Implemented |
IC0111 # 03 Y:2006 | 03 | 2006 | CONVERT FROM INDIRECT TO DIRECT FIRED SYSTEMS | $186,788 | $135,156 | Not Implemented |
IC0111 # 02 Y:2006 | 02 | 2006 | REPLACE ELECTRIC MOTORS WITH BACK PRESSURE STEAM TURBINES AND USE EXHAUST STEAM FOR PROCESS HEAT | $95,000 | $442,680 | Not Implemented |
IC0111 # 01 Y:2006 | 01 | 2006 | REPLACE STEAM JETS ON VACUUM SYSTEM WITH ELECTRIC MOTOR DRIVEN VACUUM PUMPS | $803,012 | $258,000 | Implemented |
IC0111 # 10 Y:2006 | 10 | 2006 | INSTALL / REPAIR INSULATION ON STEAM LINES | $17,406 | $19,704 | Implemented |
IC0103 # 06 Y:2005 | 06 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,336 | $941 | Not Implemented |
IC0103 # 01 Y:2005 | 01 | 2005 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $12,792 | $12,792 | Not Implemented |
IC0103 # 02 Y:2005 | 02 | 2005 | INSTALL / REPAIR INSULATION ON STEAM LINES | $8,631 | $4,680 | Not Implemented |
IC0103 # 03 Y:2005 | 03 | 2005 | REPAIR AND ELIMINATE STEAM LEAKS | $2,344 | $1,400 | Not Implemented |
IC0103 # 04 Y:2005 | 04 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,340 | $300 | Not Implemented |
IC0103 # 05 Y:2005 | 05 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $240 | $0 | Not Implemented |
IC0103 # 07 Y:2005 | 07 | 2005 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $330 | $2,800 | Not Implemented |
IC0103 # 08 Y:2005 | 08 | 2005 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $104 | $256 | Not Implemented |
IC0060 # 01 Y:2003 | 01 | 2003 | REPAIR AND ELIMINATE STEAM LEAKS | $148,006 | $13,000 | Implemented |
IC0060 # 02 Y:2003 | 02 | 2003 | INSTALL / REPAIR INSULATION ON STEAM LINES | $8,832 | $13,240 | Implemented |
IC0060 # 03 Y:2003 | 03 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $8,390 | $20,640 | Implemented |
IC0060 # 04 Y:2003 | 04 | 2003 | USE STEAM CONDENSATE FOR HOT WATER SUPPLY (NON-POTABLE) | $163,590 | $170,491 | Implemented |
IC0060 # 05 Y:2003 | 05 | 2003 | USE STEAM PRESSURE REDUCTION TO GENERATE POWER | $92,294 | $190,000 | Not Implemented |