IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

21

matching recommendations
Reset
NAICS 325180 Other Basic Inorganic Chemical Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK1015 # 05 Y:2019 05 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $427 $2,045 Implemented
OK1015 # 04 Y:2019 04 2019 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $380 $435 Not Implemented
OK1015 # 03 Y:2019 03 2019 INSTALL SET-BACK TIMERS $320 $200 Implemented
OK1015 # 02 Y:2019 02 2019 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $15,577 $17,500 Not Implemented
OK1015 # 01 Y:2019 01 2019 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $16,383 $12,752 Not Implemented
OK0969 # 03 Y:2017 03 2017 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $532 $4,727 Not Implemented
OK0969 # 08 Y:2017 08 2017 INSTALL SET-BACK TIMERS $396 $148 Not Implemented
OK0969 # 07 Y:2017 07 2017 PAY UTILITY BILLS ON TIME $4,330 $0 Implemented
OK0969 # 06 Y:2017 06 2017 OPTIMIZE PLANT POWER FACTOR $2,384 $16,995 Not Implemented
OK0969 # 05 Y:2017 05 2017 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $21,138 $23,262 Not Implemented
OK0969 # 04 Y:2017 04 2017 REPAIR AND ELIMINATE STEAM LEAKS $12,697 $2,712 Not Implemented
OK0969 # 02 Y:2017 02 2017 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $29,000 $48,139 Implemented
OK0969 # 01 Y:2017 01 2017 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $23,730 $42,000 Not Implemented
OK0710 # 01 Y:2005 01 2005 AVOID EMERGENCY REWIND OF MOTORS $18,566 $18,454 Not Implemented
OK0710 # 08 Y:2005 08 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $298 $895 Not Implemented
OK0710 # 07 Y:2005 07 2005 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $729 $30 Not Implemented
OK0710 # 06 Y:2005 06 2005 INSTALL OCCUPANCY SENSORS $467 $356 Not Implemented
OK0710 # 05 Y:2005 05 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,439 $4,746 Implemented
OK0710 # 04 Y:2005 04 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,823 $1,607 Not Implemented
OK0710 # 03 Y:2005 03 2005 INSTALL SET-BACK TIMERS $1,403 $430 Not Implemented
OK0710 # 02 Y:2005 02 2005 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,475 $3,550 Implemented