Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
52
matching recommendationsNAICS | 32519 | Other Basic Organic Chemical Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0441 # 07 Y:2024 | 07 | 2024 | INSTALL OCCUPANCY SENSORS | $671 | $1,203 | n/a |
MI0441 # 06 Y:2024 | 06 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,124 | $1,980 | n/a |
MI0441 # 05 Y:2024 | 05 | 2024 | USE SOLAR HEAT TO HEAT WATER | $2,247 | $2,602 | n/a |
MI0441 # 04 Y:2024 | 04 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,377 | $510 | n/a |
MI0441 # 03 Y:2024 | 03 | 2024 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $21,427 | $1,306 | n/a |
MI0441 # 02 Y:2024 | 02 | 2024 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $24,362 | $840 | n/a |
MI0441 # 01 Y:2024 | 01 | 2024 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $58,244 | $186,000 | n/a |
UF0512 # 07 Y:2017 | 07 | 2017 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $26,348 | $725 | Implemented |
UF0512 # 01 Y:2017 | 01 | 2017 | USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST | $401,159 | $2,500,000 | Not Implemented |
UF0512 # 06 Y:2017 | 06 | 2017 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $10,845 | $2,750 | Implemented |
UF0512 # 02 Y:2017 | 02 | 2017 | ISOLATE HOT OR COLD EQUIPMENT | $124,880 | $17,000 | Implemented |
UF0512 # 03 Y:2017 | 03 | 2017 | OPTIMIZE PLANT POWER FACTOR | $38,189 | $13,000 | Implemented |
UF0512 # 05 Y:2017 | 05 | 2017 | USE CORRECT SIZE STEAM TRAPS | $27,893 | $340 | Implemented |
UF0512 # 11 Y:2017 | 11 | 2017 | COOL COMPRESSOR AIR INTAKE WITH HEAT EXCHANGER | $2,136 | $1,562 | Not Implemented |
UF0512 # 09 Y:2017 | 09 | 2017 | INCREASE AMOUNT OF CONDENSATE RETURNED | $4,891 | $0 | Implemented |
UF0512 # 10 Y:2017 | 10 | 2017 | INSTALL COMMON HEADER ON COMPRESSORS | $3,951 | $11,185 | Implemented |
UF0512 # 08 Y:2017 | 08 | 2017 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $9,636 | $6,225 | Implemented |
UF0512 # 04 Y:2017 | 04 | 2017 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $23,030 | $40,000 | Not Implemented |
UF0512 # 12 Y:2017 | 12 | 2017 | UTILIZE OTHER METHODS TO REMOVE CONTAMINANTS | $280,764 | $300,000 | Implemented |
UF0501 # 09 Y:2017 | 09 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,020 | $482 | Implemented |
UF0501 # 08 Y:2017 | 08 | 2017 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $5,834 | $0 | Implemented |
UF0501 # 06 Y:2017 | 06 | 2017 | MODERATE COOLING TOWER OUTLET TEMPERATURE | $9,110 | $700 | Implemented |
UF0501 # 05 Y:2017 | 05 | 2017 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $29,058 | $39,050 | Implemented |
UF0501 # 04 Y:2017 | 04 | 2017 | REPAIR AND ELIMINATE STEAM LEAKS | $32,236 | $1,794 | Implemented |
UF0501 # 03 Y:2017 | 03 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $77,438 | $2,184 | Implemented |