Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
57
matching recommendationsNAICS | 325199 | All Other Basic Organic Chemical Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0632 # 01 Y:2025 | 01 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $43,631 | $322,608 | n/a |
UF0632 # 09 Y:2025 | 09 | 2025 | INSTALL TURBULATORS | $2,277 | $3,750 | n/a |
UF0632 # 10 Y:2025 | 10 | 2025 | INSTALL DE-AERATOR IN PLACE OF CONDENSATE TANK | $2,684 | $2,743 | n/a |
UF0632 # 11 Y:2025 | 11 | 2025 | USE REVERSE OSMOSIS TO CONCENTRATE MATERIAL | $3,839 | $3,079 | n/a |
UF0632 # 12 Y:2025 | 12 | 2025 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $7,429 | $20,000 | n/a |
UF0632 # 13 Y:2025 | 13 | 2025 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $1,094 | $0 | n/a |
UF0632 # 08 Y:2025 | 08 | 2025 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,170 | $2,654 | n/a |
UF0632 # 07 Y:2025 | 07 | 2025 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $4,170 | $6,785 | n/a |
UF0632 # 06 Y:2025 | 06 | 2025 | IMPROVE COMBUSTION CONTROL CAPABILITY | $4,200 | $2,000 | n/a |
UF0632 # 05 Y:2025 | 05 | 2025 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $5,526 | $20,560 | n/a |
UF0632 # 04 Y:2025 | 04 | 2025 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $12,726 | $12,000 | n/a |
UF0632 # 03 Y:2025 | 03 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $16,911 | $34,076 | n/a |
UF0632 # 02 Y:2025 | 02 | 2025 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $21,772 | $20,202 | n/a |
UF0632 # 14 Y:2025 | 14 | 2025 | IMPROVE SPACE COMFORT CONDITIONING | $1,115 | $3,888 | n/a |
MI0441 # 01 Y:2024 | 01 | 2024 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $58,244 | $186,000 | Implemented |
MI0441 # 07 Y:2024 | 07 | 2024 | INSTALL OCCUPANCY SENSORS | $671 | $1,203 | Implemented |
MI0441 # 02 Y:2024 | 02 | 2024 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $24,362 | $840 | Not Implemented |
MI0441 # 03 Y:2024 | 03 | 2024 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $21,427 | $1,306 | Implemented |
MI0441 # 04 Y:2024 | 04 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,377 | $510 | Implemented |
MI0441 # 05 Y:2024 | 05 | 2024 | USE SOLAR HEAT TO HEAT WATER | $2,247 | $2,602 | Not Implemented |
MI0441 # 06 Y:2024 | 06 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,124 | $1,980 | Implemented |
UF0512 # 06 Y:2017 | 06 | 2017 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $10,845 | $2,750 | Implemented |
UF0512 # 05 Y:2017 | 05 | 2017 | USE CORRECT SIZE STEAM TRAPS | $27,893 | $340 | Implemented |
UF0512 # 04 Y:2017 | 04 | 2017 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $23,030 | $40,000 | Not Implemented |
UF0512 # 01 Y:2017 | 01 | 2017 | USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST | $401,159 | $2,500,000 | Not Implemented |