Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
945
matching recommendationsNAICS | 325211 | Plastics Material and Resin Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LL0252 # 08 Y:2006 | 08 | 2006 | INSULATE BARE EQUIPMENT | $76 | $79 | Implemented |
MA0608 # 01 Y:2006 | 01 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $38,346 | $38,000 | Not Implemented |
MA0608 # 02 Y:2006 | 02 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $35,557 | $91,980 | Implemented |
MA0608 # 03 Y:2006 | 03 | 2006 | INCREASE AMOUNT OF CONDENSATE RETURNED | $20,310 | $45,000 | Not Implemented |
MA0608 # 04 Y:2006 | 04 | 2006 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $15,294 | $36,000 | Implemented |
MA0608 # 05 Y:2006 | 05 | 2006 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $4,181 | $83,000 | Not Implemented |
MA0608 # 06 Y:2006 | 06 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,784 | $150 | Implemented |
MA0608 # 07 Y:2006 | 07 | 2006 | INSULATE BARE EQUIPMENT | $1,575 | $2,925 | Implemented |
MA0608 # 08 Y:2006 | 08 | 2006 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $712 | $1,500 | Implemented |
MS0296 # 01 Y:2006 | 01 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $57,344 | $3,269 | Implemented |
MS0296 # 02 Y:2006 | 02 | 2006 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $44,954 | $113,910 | Not Implemented |
MS0296 # 03 Y:2006 | 03 | 2006 | REPAIR AND ELIMINATE STEAM LEAKS | $33,575 | $374 | Implemented |
MS0296 # 04 Y:2006 | 04 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,105 | $51,885 | Not Implemented |
MS0296 # 05 Y:2006 | 05 | 2006 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,082 | $6,420 | Implemented |
MS0296 # 06 Y:2006 | 06 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,895 | $12,886 | Not Implemented |
WV0338 # 01 Y:2006 | 01 | 2006 | ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE | $30,361 | $6,000 | Not Implemented |
WV0338 # 02 Y:2006 | 02 | 2006 | INSULATE BARE EQUIPMENT | $24,000 | $10,954 | Implemented |
WV0338 # 03 Y:2006 | 03 | 2006 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $17,026 | $0 | Implemented |
WV0338 # 04 Y:2006 | 04 | 2006 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $5,133 | $1,000 | Implemented |
WV0338 # 05 Y:2006 | 05 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,593 | $0 | Implemented |
WV0338 # 06 Y:2006 | 06 | 2006 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $2,611 | $45 | Implemented |
WV0338 # 07 Y:2006 | 07 | 2006 | DEVELOP A REPAIR/REPLACE POLICY | $2,505 | $709 | Implemented |
WV0338 # 08 Y:2006 | 08 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,078 | $8 | Implemented |
WV0338 # 09 Y:2006 | 09 | 2006 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $1,916 | $4,108 | Not Implemented |
WV0338 # 10 Y:2006 | 10 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,289 | $820 | Implemented |