Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
171
matching recommendationsNAICS | 32561 | Soap and Cleaning Compound Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0383 # 01 Y:2020 | 01 | 2020 | USE SOLAR HEAT TO HEAT WATER | $10,293 | $12,280 | Implemented |
MI0380 # 01 Y:2020 | 01 | 2020 | USE SOLAR HEAT TO HEAT WATER | $17,031 | $8,409 | Implemented |
MI0380 # 02 Y:2020 | 02 | 2020 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $4,433 | $12,201 | Implemented |
MI0380 # 04 Y:2020 | 04 | 2020 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,753 | $3,280 | Implemented |
MI0380 # 03 Y:2020 | 03 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,272 | $11,460 | Implemented |
MI0380 # 06 Y:2020 | 06 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,175 | $1,980 | Implemented |
MI0380 # 07 Y:2020 | 07 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $568 | $120 | Implemented |
TR0025 # 03 Y:2020 | 03 | 2020 | USE OPTIMUM THICKNESS INSULATION | $1,067 | $830 | Implemented |
TR0025 # 04 Y:2020 | 04 | 2020 | REPAIR AND ELIMINATE STEAM LEAKS | $1,683 | $130 | Implemented |
TR0025 # 06 Y:2020 | 06 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,497 | $9,060 | Implemented |
TR0025 # 02 Y:2020 | 02 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,326 | $1,145 | Implemented |
TR0025 # 01 Y:2020 | 01 | 2020 | INSULATE BARE EQUIPMENT | $657 | $440 | Implemented |
TR0025 # 05 Y:2020 | 05 | 2020 | INSTALL OCCUPANCY SENSORS | $371 | $676 | Implemented |
AS0479 # 06 Y:2020 | 06 | 2020 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,794 | $7,400 | Implemented |
AS0479 # 05 Y:2020 | 05 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,834 | $330 | Implemented |
AS0479 # 04 Y:2020 | 04 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,979 | $1,639 | Implemented |
AS0479 # 03 Y:2020 | 03 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $12,108 | $6,016 | Implemented |
AS0479 # 01 Y:2020 | 01 | 2020 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $20,215 | $200 | Implemented |
MZ0279 # 06 Y:2019 | 06 | 2019 | INSULATE BARE EQUIPMENT | $428 | $1,464 | Implemented |
CL1910 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,560 | $23,063 | Implemented |
MZ0279 # 01 Y:2019 | 01 | 2019 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,031 | $4,700 | Implemented |
MZ0279 # 04 Y:2019 | 04 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $27,794 | $6,252 | Implemented |
MZ0279 # 03 Y:2019 | 03 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,014 | $640 | Implemented |
MZ0279 # 05 Y:2019 | 05 | 2019 | RECOVER WASTE HEAT FROM EQUIPMENT | $16,719 | $14,400 | Implemented |
MZ0279 # 07 Y:2019 | 07 | 2019 | INSTALL SPECTRAL REFLECTORS / DELAMP | $19,835 | $25,600 | Implemented |