Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
865
matching recommendationsNAICS | 32599 | All Other Chemical Product and Preparation Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0457 # 02 Y:2014 | 02 | 2014 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,323 | $0 | Not Implemented |
SF0457 # 03 Y:2014 | 03 | 2014 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $10,640 | $4,356 | Not Implemented |
SF0457 # 04 Y:2014 | 04 | 2014 | INSTALL OCCUPANCY SENSORS | $4,973 | $3,386 | Implemented |
SF0457 # 05 Y:2014 | 05 | 2014 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $487 | $898 | Implemented |
SF0457 # 06 Y:2014 | 06 | 2014 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $270 | $597 | Not Implemented |
SF0457 # 07 Y:2014 | 07 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,420 | $21,352 | Implemented |
SF0457 # 08 Y:2014 | 08 | 2014 | USE SOLAR HEAT TO MAKE ELECTRICTY | $91,174 | $463,974 | Not Implemented |
CO0690 # 01 Y:2014 | 01 | 2014 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,730 | $1,460 | Implemented |
CO0690 # 02 Y:2014 | 02 | 2014 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,180 | $0 | Implemented |
CO0690 # 03 Y:2014 | 03 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $940 | $370 | Implemented |
CO0690 # 04 Y:2014 | 04 | 2014 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $5,790 | $28,490 | Not Implemented |
CO0690 # 05 Y:2014 | 05 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,080 | $5,800 | Not Implemented |
MI0246 # 01 Y:2013 | 01 | 2013 | TURN OFF EQUIPMENT WHEN NOT IN USE | $30,416 | $2,300 | Implemented |
MI0246 # 02 Y:2013 | 02 | 2013 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $14,747 | $17,000 | Implemented |
MI0246 # 03 Y:2013 | 03 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,442 | $1,660 | Implemented |
MI0246 # 04 Y:2013 | 04 | 2013 | INSTALL OCCUPANCY SENSORS | $2,851 | $417 | Not Implemented |
MI0246 # 05 Y:2013 | 05 | 2013 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,190 | $2,520 | Not Implemented |
MI0246 # 06 Y:2013 | 06 | 2013 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $2,076 | $6,910 | Not Implemented |
MI0246 # 07 Y:2013 | 07 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,508 | $4,420 | Implemented |
MI0246 # 08 Y:2013 | 08 | 2013 | PAY BILLS ON TIME TO AVOID LATE FEES | $945 | $240 | Implemented |
MI0246 # 09 Y:2013 | 09 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $876 | $80 | Implemented |
UD0887 # 01 Y:2013 | 01 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,553 | $50 | Implemented |
UD0887 # 02 Y:2013 | 02 | 2013 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $1,438 | $0 | Implemented |
UD0887 # 03 Y:2013 | 03 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $497 | $500 | Implemented |
UD0887 # 04 Y:2013 | 04 | 2013 | INSTALL SPECTRAL REFLECTORS / DELAMP | $8,763 | $2,075 | Implemented |