Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
8,415
matching recommendationsNAICS | 326 | Plastics and Rubber Products Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0940 # 03 Y:2016 | 03 | 2016 | INSULATE BARE EQUIPMENT | $15,056 | $750 | Not Implemented |
UD0940 # 04 Y:2016 | 04 | 2016 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $10,308 | $0 | Implemented |
UD0940 # 05 Y:2016 | 05 | 2016 | INSTALL OCCUPANCY SENSORS | $4,195 | $1,683 | Not Implemented |
UD0940 # 06 Y:2016 | 06 | 2016 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,717 | $1,500 | Implemented |
UD0940 # 07 Y:2016 | 07 | 2016 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $2,236 | $5,400 | Not Implemented |
UD0940 # 08 Y:2016 | 08 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,111 | $29 | Implemented |
UD0940 # 09 Y:2016 | 09 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $920 | $1,000 | Implemented |
UD0940 # 10 Y:2016 | 10 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,879 | $3,100 | Not Implemented |
UD0940 # 11 Y:2016 | 11 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,440 | $2,275 | Not Implemented |
UD0940 # 12 Y:2016 | 12 | 2016 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $1,892 | $5,000 | Implemented |
OK0932 # 01 Y:2016 | 01 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,787 | $14,515 | Not Implemented |
OK0932 # 02 Y:2016 | 02 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,916 | $7,335 | Not Implemented |
OK0932 # 03 Y:2016 | 03 | 2016 | USE RADIANT HEATER FOR SPOT HEATING | $3,703 | $11,940 | Not Implemented |
OK0932 # 04 Y:2016 | 04 | 2016 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,740 | $2,829 | Not Implemented |
OK0932 # 05 Y:2016 | 05 | 2016 | RECOVER WASTE HEAT FROM EQUIPMENT | $481 | $460 | Not Implemented |
OK0932 # 06 Y:2016 | 06 | 2016 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $52 | $175 | Not Implemented |
OK0932 # 07 Y:2016 | 07 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $240 | $125 | Not Implemented |
OK0932 # 08 Y:2016 | 08 | 2016 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $3,679 | $12,315 | Not Implemented |
OK0932 # 09 Y:2016 | 09 | 2016 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $429 | $0 | Not Implemented |
OK0932 # 10 Y:2016 | 10 | 2016 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $6,093 | $30,000 | Not Implemented |
OK0932 # 11 Y:2016 | 11 | 2016 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $3,216 | $871 | Not Implemented |
OK0932 # 12 Y:2016 | 12 | 2016 | OPERATE BOILERS ON HIGH FIRE SETTING | $16,492 | $0 | Implemented |
OK0932 # 13 Y:2016 | 13 | 2016 | REPAIR AND ELIMINATE STEAM LEAKS | $4,272 | $1,100 | Implemented |
OK0932 # 14 Y:2016 | 14 | 2016 | SHUT OFF STEAM TRAPS ON SUPER HEATED STEAM LINES WHEN NOT IN USE | $4,116 | $0 | Not Implemented |
SD0521 # 01 Y:2016 | 01 | 2016 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $63,923 | $80,120 | Not Implemented |