Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
8,415
matching recommendationsNAICS | 326 | Plastics and Rubber Products Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0231 # 09 Y:2003 | 09 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $995 | $2,905 | Not Implemented |
MS0231 # 10 Y:2003 | 10 | 2003 | INSTALL TIMERS AND/OR THERMOSTATS | $152 | $119 | Implemented |
MS0231 # 11 Y:2003 | 11 | 2003 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $120 | $10 | Implemented |
CO0527 # 01 Y:2003 | 01 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,000 | $15,440 | Not Implemented |
CO0527 # 02 Y:2003 | 02 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,260 | $550 | Not Implemented |
CO0527 # 03 Y:2003 | 03 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $467 | $518 | Not Implemented |
CO0527 # 04 Y:2003 | 04 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $960 | $2,310 | Not Implemented |
CO0527 # 05 Y:2003 | 05 | 2003 | INSULATE BARE EQUIPMENT | $600 | $1,270 | Not Implemented |
UU0048 # 01 Y:2003 | 01 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,985 | $306 | Not Implemented |
UU0048 # 02 Y:2003 | 02 | 2003 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $440 | $432 | Not Implemented |
UU0048 # 03 Y:2003 | 03 | 2003 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $14,920 | $40,000 | Not Implemented |
UU0048 # 04 Y:2003 | 04 | 2003 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $19,330 | $9,176 | Implemented |
UU0048 # 05 Y:2003 | 05 | 2003 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $1,040 | $947 | Not Implemented |
UU0048 # 06 Y:2003 | 06 | 2003 | REPAIR OR REPLACE STEAM TRAPS | $16,294 | $5,000 | Not Implemented |
UU0048 # 07 Y:2003 | 07 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $480 | $0 | Not Implemented |
UU0048 # 08 Y:2003 | 08 | 2003 | INSTALL / REPAIR INSULATION ON STEAM LINES | $493 | $518 | Not Implemented |
UU0048 # 09 Y:2003 | 09 | 2003 | RECOVER AND REUSE COOLING WATER | $9,920 | $7,907 | Not Implemented |
UU0048 # 10 Y:2003 | 10 | 2003 | REUSE / RECYCLE/ SELL RUBBER PRODUCTS | $1 | $0 | Not Implemented |
NC0260 # 01 Y:2003 | 01 | 2003 | INSTALL OCCUPANCY SENSORS | $396 | $208 | Not Implemented |
NC0260 # 02 Y:2003 | 02 | 2003 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $19,437 | $8,000 | Not Implemented |
NC0260 # 03 Y:2003 | 03 | 2003 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $16,074 | $9,000 | Not Implemented |
NC0260 # 04 Y:2003 | 04 | 2003 | RE-SIZE CHARGING OPENINGS OR ADD A MOVABLE DOOR ON EQUIPMENT | $606 | $176 | Not Implemented |
NC0260 # 05 Y:2003 | 05 | 2003 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $11,263 | $16,548 | Not Implemented |
NC0260 # 06 Y:2003 | 06 | 2003 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $234 | $0 | Not Implemented |
NC0260 # 07 Y:2003 | 07 | 2003 | DEVELOP A REPAIR/REPLACE POLICY | $347 | $260 | Not Implemented |