Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
348
matching recommendationsNAICS | 326 | Plastics and Rubber Products Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CL1911 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $46,300 | $34,518 | Not Implemented |
WV0585 # 10 Y:2019 | 10 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,014 | $1,303 | Implemented |
WV0585 # 09 Y:2019 | 09 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,529 | $250 | Not Implemented |
WV0585 # 08 Y:2019 | 08 | 2019 | DEVELOP A REPAIR/REPLACE POLICY | $5,125 | $1,450 | Implemented |
WV0585 # 07 Y:2019 | 07 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,160 | $1,100 | Implemented |
WV0585 # 06 Y:2019 | 06 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,658 | $9,998 | Implemented |
WV0585 # 05 Y:2019 | 05 | 2019 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $9,261 | $0 | Implemented |
WV0585 # 04 Y:2019 | 04 | 2019 | UPGRADE CONTROLS ON COMPRESSORS | $18,306 | $16,750 | Not Implemented |
WV0585 # 03 Y:2019 | 03 | 2019 | INSULATE BARE EQUIPMENT | $30,373 | $10,462 | Not Implemented |
WV0585 # 02 Y:2019 | 02 | 2019 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $33,124 | $77,800 | Not Implemented |
WV0585 # 01 Y:2019 | 01 | 2019 | RECYCLE WHITE WATER | $175,950 | $82,900 | Not Implemented |
IC0221 # 03 Y:2019 | 03 | 2019 | INSULATE BARE EQUIPMENT | $8,629 | $5,550 | Not Implemented |
IC0221 # 02 Y:2019 | 02 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,682 | $4,200 | Implemented |
IC0221 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,226 | $7,471 | Implemented |
MZ0278 # 10 Y:2019 | 10 | 2019 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $4,709 | $200 | Implemented |
MZ0278 # 09 Y:2019 | 09 | 2019 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $5,558 | $870 | Implemented |
MZ0278 # 08 Y:2019 | 08 | 2019 | RECOVER WASTE HEAT FROM EQUIPMENT | $35,571 | $11,900 | Not Implemented |
MZ0278 # 07 Y:2019 | 07 | 2019 | UPGRADE CONTROLS ON COMPRESSORS | $42,284 | $13,051 | Implemented |
MZ0278 # 06 Y:2019 | 06 | 2019 | INSULATE BARE EQUIPMENT | $45,917 | $2,907 | Implemented |
MZ0278 # 05 Y:2019 | 05 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $53,880 | $7,750 | Not Implemented |
MZ0278 # 04 Y:2019 | 04 | 2019 | REDUCE SCRAP PRODUCTION | $126,263 | $207,500 | Implemented |
MZ0278 # 03 Y:2019 | 03 | 2019 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $176,232 | $3,250 | Implemented |
MZ0278 # 02 Y:2019 | 02 | 2019 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $382,507 | $601,250 | Implemented |
MZ0278 # 01 Y:2019 | 01 | 2019 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $902,475 | $6,762,500 | Implemented |
SD0586 # 08 Y:2019 | 08 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,943 | $750 | Not Implemented |