Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
199
matching recommendationsNAICS | 3261 | Plastics Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0614 # 05 Y:2024 | 05 | 2024 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $15,952 | $39,000 | Implemented |
UF0614 # 12 Y:2024 | 12 | 2024 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $10,444 | $4,280 | Implemented |
UF0614 # 13 Y:2024 | 13 | 2024 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $27,969 | $60,000 | Implemented |
UF0614 # 10 Y:2024 | 10 | 2024 | ADJUST VENTS TO MINIMIZE ENERGY USE | $2,337 | $1,797 | Implemented |
UF0614 # 07 Y:2024 | 07 | 2024 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $6,473 | $24,140 | Implemented |
UF0614 # 14 Y:2024 | 14 | 2024 | IMPROVE SPACE COMFORT CONDITIONING | $5,321 | $3,260 | Implemented |
UF0614 # 06 Y:2024 | 06 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,910 | $351 | Implemented |
UF0614 # 03 Y:2024 | 03 | 2024 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $24,631 | $18,563 | Implemented |
UF0614 # 02 Y:2024 | 02 | 2024 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $35,722 | $41,798 | Implemented |
UF0615 # 05 Y:2024 | 05 | 2024 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $8,911 | $816 | Implemented |
UF0615 # 09 Y:2024 | 09 | 2024 | UPGRADE CONTROLS ON COMPRESSORS | $2,456 | $4,000 | Implemented |
UF0615 # 11 Y:2024 | 11 | 2024 | IMPROVE SPACE COMFORT CONDITIONING | $20,106 | $3,020 | Implemented |
UF0615 # 06 Y:2024 | 06 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,078 | $355 | Implemented |
UF0615 # 07 Y:2024 | 07 | 2024 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $8,021 | $5,898 | Implemented |
UF0615 # 04 Y:2024 | 04 | 2024 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $14,133 | $22,755 | Implemented |
UF0615 # 02 Y:2024 | 02 | 2024 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $66,500 | $73,000 | Implemented |
UF0615 # 03 Y:2024 | 03 | 2024 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $41,878 | $24,095 | Implemented |
UF0615 # 10 Y:2024 | 10 | 2024 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $4,769 | $2,352 | Implemented |
UF0594 # 08 Y:2023 | 08 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,918 | $756 | Implemented |
UF0594 # 07 Y:2023 | 07 | 2023 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $3,181 | $6,536 | Implemented |
MI0422 # 03 Y:2023 | 03 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $21,293 | $580 | Implemented |
MI0422 # 06 Y:2023 | 06 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $394 | $0 | Implemented |
MI0422 # 05 Y:2023 | 05 | 2023 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $2,579 | $4,001 | Implemented |
MI0422 # 04 Y:2023 | 04 | 2023 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $4,309 | $280 | Implemented |
UF0592 # 05 Y:2023 | 05 | 2023 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $9,922 | $11,796 | Implemented |