Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
7,072
matching recommendationsNAICS | 3261 | Plastics Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0405 # 05 Y:2010 | 05 | 2010 | DEVELOP A REPAIR/REPLACE POLICY | $1,917 | $804 | Not Implemented |
WV0405 # 06 Y:2010 | 06 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,359 | $588 | Implemented |
WV0405 # 07 Y:2010 | 07 | 2010 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $1,180 | $10,000 | Not Implemented |
WV0405 # 08 Y:2010 | 08 | 2010 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $747 | $1,000 | Implemented |
WV0405 # 09 Y:2010 | 09 | 2010 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $398 | $342 | Not Implemented |
WV0405 # 10 Y:2010 | 10 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $367 | $27 | Implemented |
WV0405 # 11 Y:2010 | 11 | 2010 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $194 | $0 | Not Implemented |
TT0049 # 01 Y:2010 | 01 | 2010 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $5,280 | $9,600 | Not Implemented |
TT0049 # 02 Y:2010 | 02 | 2010 | REPAIR OR REPLACE STEAM TRAPS | $9,803 | $4,000 | Not Implemented |
TT0049 # 03 Y:2010 | 03 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,257 | $50 | Not Implemented |
TT0049 # 04 Y:2010 | 04 | 2010 | DEVELOP A REPAIR/REPLACE POLICY | $16,200 | $18,200 | Not Implemented |
TT0049 # 05 Y:2010 | 05 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $21,756 | $173,505 | Implemented |
TT0049 # 06 Y:2010 | 06 | 2010 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $10,723 | $0 | Not Implemented |
MZ0048 # 01 Y:2010 | 01 | 2010 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $12,738 | $3,000 | Not Implemented |
MZ0048 # 02 Y:2010 | 02 | 2010 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,520 | $1,160 | Implemented |
MZ0048 # 03 Y:2010 | 03 | 2010 | OPTIMIZE PLANT POWER FACTOR | $36,058 | $92,296 | Implemented |
MZ0048 # 04 Y:2010 | 04 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,649 | $0 | Not Implemented |
MZ0048 # 05 Y:2010 | 05 | 2010 | TURN OFF EQUIPMENT WHEN NOT IN USE | $5,639 | $0 | Implemented |
MZ0048 # 06 Y:2010 | 06 | 2010 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $11,307 | $5,859 | Not Implemented |
MZ0048 # 07 Y:2010 | 07 | 2010 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $62,629 | $5,600 | Not Implemented |
MS0354 # 01 Y:2010 | 01 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,040 | $6,573 | Not Implemented |
MS0354 # 02 Y:2010 | 02 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,328 | $356 | Not Implemented |
MS0354 # 03 Y:2010 | 03 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $524 | $1,365 | Not Implemented |
MS0354 # 04 Y:2010 | 04 | 2010 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $324 | $490 | Not Implemented |
IC0170 # 01 Y:2010 | 01 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $376 | $814 | Implemented |