IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

7,072

matching recommendations
Reset
NAICS 3261 Plastics Product Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SF0547 # 08 Y:2019 08 2019 AIR CONDITION ONLY SPACE NECESSARY $17,743 $33,601 Implemented
SF0547 # 09 Y:2019 09 2019 INSULATE BARE EQUIPMENT $3,114 $6,574 Implemented
SF0547 # 10 Y:2019 10 2019 USE SOLAR HEAT TO MAKE ELECTRICTY $120,071 $1,107,885 Not Implemented
NC0641 # 01 Y:2019 01 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,164 $120 Not Implemented
NC0641 # 02 Y:2019 02 2019 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $18,554 $21,000 Not Implemented
NC0641 # 03 Y:2019 03 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $29,143 $35,000 Implemented
NC0641 # 04 Y:2019 04 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,183 $16,246 Not Implemented
OK1017 # 01 Y:2019 01 2019 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $7,604 $17,500 Not Implemented
OK1017 # 02 Y:2019 02 2019 INSTALL / REPAIR INSULATION ON STEAM LINES $10,627 $231 Not Implemented
OK1017 # 03 Y:2019 03 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $22,220 $22,288 Not Implemented
OK1017 # 04 Y:2019 04 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,214 $3,590 Not Implemented
OK1017 # 05 Y:2019 05 2019 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $6,164 $0 Not Implemented
CL1911 # 01 Y:2019 01 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $46,300 $34,518 Not Implemented
CL1911 # 02 Y:2019 02 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $21,115 $4,000 Not Implemented
CL1911 # 03 Y:2019 03 2019 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $1,429 $250 Not Implemented
CL1911 # 04 Y:2019 04 2019 KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE $7,094 $0 Not Implemented
IC0221 # 01 Y:2019 01 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $11,226 $7,471 Implemented
IC0221 # 02 Y:2019 02 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,682 $4,200 Implemented
IC0221 # 03 Y:2019 03 2019 INSULATE BARE EQUIPMENT $8,629 $5,550 Not Implemented
MZ0278 # 01 Y:2019 01 2019 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL $902,475 $6,762,500 Implemented
MZ0278 # 02 Y:2019 02 2019 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $382,507 $601,250 Implemented
MZ0278 # 03 Y:2019 03 2019 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $176,232 $3,250 Implemented
MZ0278 # 04 Y:2019 04 2019 REDUCE SCRAP PRODUCTION $126,263 $207,500 Implemented
MZ0278 # 05 Y:2019 05 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $53,880 $7,750 Not Implemented
MZ0278 # 06 Y:2019 06 2019 INSULATE BARE EQUIPMENT $45,917 $2,907 Implemented