Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
472
matching recommendationsNAICS | 32611 | Plastics Packaging Materials and Unlaminated Film and Sheet Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UW2202 # 01 Y:2022 | 01 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $16,645 | $10,782 | Implemented |
UW2202 # 02 Y:2022 | 02 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,233 | $12,913 | Implemented |
UW2202 # 03 Y:2022 | 03 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,538 | $9,763 | Implemented |
UW2202 # 04 Y:2022 | 04 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $135,581 | $876,160 | Implemented |
MI0406 # 06 Y:2022 | 06 | 2022 | ELIMINATE/REDUCE AN OPERATION | $4,770 | $960 | Implemented |
MI0406 # 05 Y:2022 | 05 | 2022 | OPTIMIZE PLANT POWER FACTOR | $5,579 | $15,821 | Implemented |
MI0406 # 04 Y:2022 | 04 | 2022 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $6,468 | $15,450 | Implemented |
MI0406 # 03 Y:2022 | 03 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,550 | $2,031 | Implemented |
MI0406 # 02 Y:2022 | 02 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,075 | $5,674 | Implemented |
MI0406 # 01 Y:2022 | 01 | 2022 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $17,298 | $45,090 | Implemented |
MA0829 # 03 Y:2022 | 03 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,700 | $4,400 | Implemented |
MA0829 # 06 Y:2022 | 06 | 2022 | SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS | $2,891 | $4,445 | Implemented |
MA0829 # 07 Y:2022 | 07 | 2022 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,594 | $5,100 | Implemented |
LE0516 # 01 Y:2021 | 01 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,511 | $200 | Implemented |
LE0516 # 02 Y:2021 | 02 | 2021 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,124 | $1,200 | Implemented |
UU0172 # 01 Y:2021 | 01 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,439 | $15,243 | Implemented |
UU0172 # 05 Y:2021 | 05 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,814 | $7,952 | Implemented |
UU0172 # 06 Y:2021 | 06 | 2021 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $3,039 | $17,334 | Implemented |
UU0172 # 07 Y:2021 | 07 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,543 | $100 | Implemented |
UU0172 # 08 Y:2021 | 08 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,268 | $212 | Implemented |
UU0172 # 09 Y:2021 | 09 | 2021 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,679 | $1,200 | Implemented |
LE0491 # 01 Y:2020 | 01 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $26,358 | $20,000 | Implemented |
LE0491 # 02 Y:2020 | 02 | 2020 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $16,658 | $14,000 | Implemented |
LE0491 # 04 Y:2020 | 04 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,952 | $8,712 | Implemented |
LE0488 # 07 Y:2020 | 07 | 2020 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $2,905 | $9,300 | Implemented |