Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
219
matching recommendationsNAICS | 32616 | Plastics Bottle Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0440 # 04 Y:2017 | 04 | 2017 | RECOVER WASTE HEAT FROM EQUIPMENT | $41,418 | $13,000 | Implemented |
LE0440 # 03 Y:2017 | 03 | 2017 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $21,749 | $3,000 | Implemented |
LE0440 # 02 Y:2017 | 02 | 2017 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $97,167 | $5,000 | Implemented |
LE0440 # 01 Y:2017 | 01 | 2017 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $14,163 | $17 | Implemented |
MZ0235 # 07 Y:2017 | 07 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $933 | $300 | Implemented |
MZ0235 # 05 Y:2017 | 05 | 2017 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,640 | $1,000 | Implemented |
MZ0235 # 04 Y:2017 | 04 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,101 | $1,623 | Implemented |
MZ0235 # 03 Y:2017 | 03 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,672 | $13,565 | Implemented |
MZ0235 # 01 Y:2017 | 01 | 2017 | OPTIMIZE PLANT POWER FACTOR | $23,631 | $11,250 | Implemented |
TT0185 # 02 Y:2017 | 02 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $114,605 | $150,000 | Implemented |
TT0185 # 01 Y:2017 | 01 | 2017 | UPGRADE CONTROLS ON COMPRESSORS | $173,199 | $5,000 | Implemented |
TT0185 # 03 Y:2017 | 03 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,276 | $1,250 | Implemented |
TT0185 # 05 Y:2017 | 05 | 2017 | APPLY FOR INVESTMENT INCENTIVES | $2,174 | $40 | Implemented |
TT0185 # 06 Y:2017 | 06 | 2017 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,425 | $1,425 | Implemented |
AM0724 # 07 Y:2017 | 07 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $235 | $200 | Implemented |
AM0724 # 05 Y:2017 | 05 | 2017 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,020 | $0 | Implemented |
AM0724 # 04 Y:2017 | 04 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,040 | $4,690 | Implemented |
AM0724 # 02 Y:2017 | 02 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,720 | $0 | Implemented |
AM0724 # 08 Y:2017 | 08 | 2017 | INSULATE BARE EQUIPMENT | $126 | $210 | Implemented |
OK0938 # 02 Y:2016 | 02 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $45,405 | $59,664 | Implemented |
OK0938 # 05 Y:2016 | 05 | 2016 | INSTALL SET-BACK TIMERS | $317 | $344 | Implemented |
OK0938 # 09 Y:2016 | 09 | 2016 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,693 | $3,236 | Implemented |
OK0938 # 11 Y:2016 | 11 | 2016 | OPTIMIZE PLANT POWER FACTOR | $26,300 | $47,542 | Implemented |
WM0083 # 06 Y:2016 | 06 | 2016 | INSTALL OCCUPANCY SENSORS | $1,673 | $1,425 | Implemented |
WM0083 # 07 Y:2016 | 07 | 2016 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,105 | $2,490 | Implemented |