Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
227
matching recommendationsNAICS | 326160 | Plastics Bottle Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
DL0194 # 04 Y:2021 | 04 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $11,663 | $1,698 | Implemented |
DL0194 # 03 Y:2021 | 03 | 2021 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,097 | $1,527 | Implemented |
DL0194 # 01 Y:2021 | 01 | 2021 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $3,325 | $475 | Implemented |
NL0053 # 08 Y:2020 | 08 | 2020 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,080 | $56 | Implemented |
NL0053 # 06 Y:2020 | 06 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,013 | $1,500 | Implemented |
NL0053 # 05 Y:2020 | 05 | 2020 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $6,360 | $56 | Implemented |
NL0053 # 04 Y:2020 | 04 | 2020 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $9,704 | $12,000 | Implemented |
NL0053 # 03 Y:2020 | 03 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,267 | $4,456 | Implemented |
NL0053 # 02 Y:2020 | 02 | 2020 | KEEP EQUIPMENT CLEAN | $24,724 | $8,528 | Implemented |
TT0241 # 08 Y:2020 | 08 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,202 | $20 | Implemented |
TT0241 # 04 Y:2020 | 04 | 2020 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $18,441 | $75,000 | Implemented |
TT0241 # 11 Y:2020 | 11 | 2020 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $307 | $680 | Implemented |
TT0241 # 02 Y:2020 | 02 | 2020 | UPGRADE CONTROLS ON COMPRESSORS | $54,178 | $300 | Implemented |
TT0241 # 03 Y:2020 | 03 | 2020 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $49,818 | $14,600 | Implemented |
TT0241 # 05 Y:2020 | 05 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,106 | $530 | Implemented |
TT0241 # 07 Y:2020 | 07 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,304 | $3,360 | Implemented |
TT0241 # 10 Y:2020 | 10 | 2020 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $404 | $1,000 | Implemented |
TT0241 # 12 Y:2020 | 12 | 2020 | INSTALL / REPAIR INSULATION ON STEAM LINES | $74 | $269 | Implemented |
TT0241 # 09 Y:2020 | 09 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,651 | $6,000 | Implemented |
OR0732 # 02 Y:2020 | 02 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $20,378 | $0 | Implemented |
SU0488 # 02 Y:2019 | 02 | 2019 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $1,216 | $264 | Implemented |
WV0577 # 02 Y:2019 | 02 | 2019 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $11,817 | $1,000 | Implemented |
WV0577 # 06 Y:2019 | 06 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,313 | $5,306 | Implemented |
WV0577 # 05 Y:2019 | 05 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,439 | $0 | Implemented |
WV0577 # 04 Y:2019 | 04 | 2019 | DEVELOP A REPAIR/REPLACE POLICY | $9,446 | $1,823 | Implemented |