Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,921
matching recommendationsNAICS | 32619 | Other Plastics Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0488 # 10 Y:2012 | 10 | 2012 | AIR CONDITION ONLY SPACE NECESSARY | $1,073 | $70 | Not Implemented |
IA0488 # 11 Y:2012 | 11 | 2012 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,909 | $743 | Not Implemented |
OR0593 # 01 Y:2012 | 01 | 2012 | USE MORE EFFICIENT ADHESIVE APPLICATORS | $72,379 | $43,800 | Not Implemented |
OR0593 # 02 Y:2012 | 02 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,751 | $4,751 | Implemented |
OR0593 # 03 Y:2012 | 03 | 2012 | AVOID COOLING OF PROCESS STREAMS OR MATERIALS THAT MUST SUBSEQUENTLY BE HEATED | $2,514 | $900 | Not Implemented |
OR0593 # 04 Y:2012 | 04 | 2012 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $930 | $2,250 | Not Implemented |
OR0593 # 05 Y:2012 | 05 | 2012 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $8,590 | $34,684 | Not Implemented |
BS0004 # 01 Y:2012 | 01 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,092 | $272 | Implemented |
BS0004 # 02 Y:2012 | 02 | 2012 | IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS | $2,756 | $802 | Implemented |
BS0004 # 03 Y:2012 | 03 | 2012 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $2,382 | $5,000 | Not Implemented |
BS0004 # 04 Y:2012 | 04 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,570 | $3,866 | Not Implemented |
BS0004 # 05 Y:2012 | 05 | 2012 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $653 | $885 | Not Implemented |
BS0004 # 06 Y:2012 | 06 | 2012 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $6,840 | $34 | Implemented |
BS0004 # 07 Y:2012 | 07 | 2012 | REUSE / RECYCLE/ SELL PAPER PRODUCTS | $1,240 | $119 | Not Implemented |
OR0585 # 02 Y:2012 | 02 | 2012 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $2,690 | $2,000 | Not Implemented |
OR0585 # 03 Y:2012 | 03 | 2012 | INSTALL TIMERS AND/OR THERMOSTATS | $1,776 | $500 | Not Implemented |
OR0585 # 04 Y:2012 | 04 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,028 | $2,305 | Implemented |
OR0585 # 05 Y:2012 | 05 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,171 | $1,000 | Not Implemented |
OR0585 # 06 Y:2012 | 06 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,942 | $1,000 | Not Implemented |
OR0585 # 07 Y:2012 | 07 | 2012 | INSTALL OCCUPANCY SENSORS | $13,449 | $24,282 | Not Implemented |
OR0585 # 08 Y:2012 | 08 | 2012 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $16,379 | $16,379 | Not Implemented |
OR0585 # 09 Y:2012 | 09 | 2012 | USE SOLAR HEAT TO MAKE ELECTRICTY | $7,083 | $47,838 | Not Implemented |
OR0585 # 10 Y:2012 | 10 | 2012 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $8,580 | $0 | Not Implemented |
OR0585 # 11 Y:2012 | 11 | 2012 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $12,086 | $16,390 | Implemented |
OR0585 # 01 Y:2012 | 01 | 2012 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $8,836 | $7,417 | Not Implemented |