Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
154
matching recommendationsNAICS | 326211 | Tire Manufacturing (except Retreading) |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UA0112 # 05 Y:2013 | 05 | 2013 | INSTALL TIMERS AND/OR THERMOSTATS | $1,143 | $520 | Not Implemented |
SU0346 # 01 Y:2013 | 01 | 2013 | USE SYNTHETIC LUBRICANT | $24,796 | $0 | Implemented |
SU0346 # 02 Y:2013 | 02 | 2013 | TURN OFF EQUIPMENT WHEN NOT IN USE | $119 | $0 | Implemented |
SU0346 # 03 Y:2013 | 03 | 2013 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $9,608 | $780 | Not Implemented |
SU0346 # 04 Y:2013 | 04 | 2013 | UPGRADE OBSOLETE EQUIPMENT | $304 | $1,295 | Implemented |
SU0346 # 05 Y:2013 | 05 | 2013 | DISCONNECT BALLASTS | $4,434 | $21,152 | Implemented |
SU0346 # 06 Y:2013 | 06 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,803 | $8,868 | Implemented |
UA0098 # 01 Y:2013 | 01 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $55,414 | $35,390 | Implemented |
UA0098 # 02 Y:2013 | 02 | 2013 | UPGRADE CONTROLS ON COMPRESSORS | $51,977 | $20,000 | Implemented |
UA0098 # 03 Y:2013 | 03 | 2013 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $25,411 | $3,500 | Implemented |
UA0098 # 04 Y:2013 | 04 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $69,733 | $36,138 | Not Implemented |
UA0098 # 05 Y:2013 | 05 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,024 | $34,540 | Not Implemented |
UA0098 # 06 Y:2013 | 06 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $9,139 | $22,860 | Not Implemented |
UA0085 # 01 Y:2012 | 01 | 2012 | USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST | $6,264,801 | $14,443,176 | Not Implemented |
UA0085 # 02 Y:2012 | 02 | 2012 | INSTALL / REPAIR INSULATION ON STEAM LINES | $164,656 | $57,024 | Implemented |
UA0085 # 03 Y:2012 | 03 | 2012 | USE STEAM PRESSURE REDUCTION TO GENERATE POWER | $86,957 | $214,808 | Not Implemented |
UA0085 # 04 Y:2012 | 04 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $10,936 | $7,682 | Not Implemented |
UA0085 # 05 Y:2012 | 05 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $151,364 | $35,390 | Implemented |
UA0085 # 06 Y:2012 | 06 | 2012 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $146,229 | $68,100 | Not Implemented |
UA0085 # 07 Y:2012 | 07 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $58,443 | $1,920 | Implemented |
UA0085 # 08 Y:2012 | 08 | 2012 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $48,968 | $131,587 | Not Implemented |
UA0085 # 09 Y:2012 | 09 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $349,571 | $177,363 | Not Implemented |
UA0085 # 10 Y:2012 | 10 | 2012 | INSTALL DESICCANT HUMIDITY CONTROL SYSTEM | $529,960 | $400,000 | Not Implemented |
SU0318 # 01 Y:2012 | 01 | 2012 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $12,626 | $0 | Not Implemented |
SU0318 # 02 Y:2012 | 02 | 2012 | USE SYNTHETIC LUBRICANT | $7,917 | $0 | Implemented |