IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

31

matching recommendations
Reset
NAICS 327 Nonmetallic Mineral Product Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0774 # 02 Y:2023 02 2023 RE-SIZE CHARGING OPENINGS OR ADD A MOVABLE DOOR ON EQUIPMENT $22,803 $17,436 n/a
OR0774 # 03 Y:2023 03 2023 UPGRADE CONTROLS ON COMPRESSORS $10,951 $10,710 n/a
OR0774 # 04 Y:2023 04 2023 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $1,255 $1,480 n/a
OR0774 # 01 Y:2023 01 2023 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $27,206 $88,913 n/a
OR0649 # 06 Y:2015 06 2015 USE SOLAR HEAT TO MAKE ELECTRICTY $23,387 $10,298 Not Implemented
OR0649 # 05 Y:2015 05 2015 TURN OFF EQUIPMENT WHEN NOT IN USE $1,536 $438 Not Implemented
OR0649 # 04 Y:2015 04 2015 CONVERT LIQUID HEATERS FROM UNDERFIRING TO IMMERSION OR SUBMERSION HEATING $5,913 $4,455 Not Implemented
OR0649 # 03 Y:2015 03 2015 TURN OFF EQUIPMENT WHEN NOT IN USE $2,825 $0 Not Implemented
OR0649 # 02 Y:2015 02 2015 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,484 $2,065 Implemented
OR0649 # 01 Y:2015 01 2015 TURN OFF EQUIPMENT WHEN NOT IN USE $18,604 $16,250 Not Implemented
OR0649 # 07 Y:2015 07 2015 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $572 $1,000 Not Implemented
OR0649 # 10 Y:2015 10 2015 INSTALL OCCUPANCY SENSORS $1,371 $2,065 Not Implemented
OR0649 # 11 Y:2015 11 2015 RECOVER WASTE HEAT FROM EQUIPMENT $4,941 $19,500 Implemented
OR0649 # 08 Y:2015 08 2015 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,277 $2,139 Implemented
OR0649 # 09 Y:2015 09 2015 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,638 $1,819 Implemented
OR0504 # 01 Y:2006 01 2006 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER $64,300 $20,000 Implemented
OR0504 # 02 Y:2006 02 2006 REPLACE STEAM JETS ON VACUUM SYSTEM WITH ELECTRIC MOTOR DRIVEN VACUUM PUMPS $22,500 $44,500 Implemented
OR0504 # 03 Y:2006 03 2006 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL $84,100 $0 Not Implemented
OR0504 # 04 Y:2006 04 2006 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL $28,000 $0 Not Implemented
OR0504 # 05 Y:2006 05 2006 MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION $23,000 $0 Implemented
OR0504 # 06 Y:2006 06 2006 REDESIGN PROCESS $6,100 $5,000 Not Implemented
OR0504 # 07 Y:2006 07 2006 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $2,500 $1,000 Not Implemented
OR0482 # 04 Y:2005 04 2005 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $3,526 $0 Implemented
OR0482 # 03 Y:2005 03 2005 COMBINE UTILITY METERS $1,500 $4,000 Not Implemented
OR0482 # 02 Y:2005 02 2005 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $60,800 $101,000 Not Implemented