Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

47

matching recommendations
Reset
NAICS 327 Nonmetallic Mineral Product Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UU0207 # 04 Y:2022 04 2022 OPTIMIZE PLANT POWER FACTOR $4,008 $3,433 Implemented
UU0207 # 03 Y:2022 03 2022 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $6,884 $750 Implemented
UU0207 # 01 Y:2022 01 2022 USE SOLAR HEAT TO HEAT WATER $15,757 $75,487 Not Implemented
UU0207 # 02 Y:2022 02 2022 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $7,250 $5,000 Not Implemented
UU0207 # 05 Y:2022 05 2022 RECOVER WASTE HEAT FROM EQUIPMENT $1,912 $1,585 Implemented
UU0207 # 06 Y:2022 06 2022 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $850 $1,000 Implemented
UU0207 # 08 Y:2022 08 2022 LOWER COMPRESSOR PRESSURE THROUGH A/C SYSTEM MODIFICATION $265 $750 Implemented
UU0207 # 07 Y:2022 07 2022 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $626 $1,700 Implemented
UU0181 # 02 Y:2021 02 2021 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $22,604 $16,880 Implemented
UU0181 # 01 Y:2021 01 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $26,862 $88,688 Implemented
UU0181 # 05 Y:2021 05 2021 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,737 $860 Implemented
UU0181 # 04 Y:2021 04 2021 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $8,017 $14,979 Implemented
UU0181 # 03 Y:2021 03 2021 INSULATE BARE EQUIPMENT $20,172 $4,900 Not Implemented
UU0159 # 05 Y:2020 05 2020 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $8,454 $16,900 Not Implemented
UU0159 # 04 Y:2020 04 2020 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $10,384 $1,000 Not Implemented
UU0159 # 03 Y:2020 03 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $38,476 $12,000 Implemented
UU0159 # 02 Y:2020 02 2020 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $47,066 $8,500 Implemented
UU0159 # 01 Y:2020 01 2020 USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR $190,938 $844,579 Not Implemented
UU0134 # 03 Y:2018 03 2018 USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS $8,796 $22,888 Not Implemented
UU0134 # 04 Y:2018 04 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,606 $2,052 Not Implemented
UU0134 # 05 Y:2018 05 2018 KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE $1,549 $0 Implemented
UU0134 # 01 Y:2018 01 2018 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $599,971 $264,049 Not Implemented
UU0134 # 02 Y:2018 02 2018 IMPROVE COMBUSTION CONTROL CAPABILITY $19,372 $15,000 Not Implemented
UU0133 # 01 Y:2018 01 2018 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $473,255 $175,000 Not Implemented
UU0133 # 05 Y:2018 05 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,767 $5,679 Implemented