Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
38
matching recommendationsNAICS | 32711 | Pottery, Ceramics, and Plumbing Fixture Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0635 # 04 Y:2022 | 04 | 2022 | UPGRADE CONTROLS ON COMPRESSORS | $3,209 | $6,354 | Not Implemented |
WV0635 # 01 Y:2022 | 01 | 2022 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $9,179 | $6,500 | Not Implemented |
WV0635 # 02 Y:2022 | 02 | 2022 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $4,325 | $5,360 | Not Implemented |
WV0635 # 06 Y:2022 | 06 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,309 | $218 | Implemented |
WV0635 # 11 Y:2022 | 11 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $57 | $88 | Implemented |
WV0635 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,990 | $4,945 | Implemented |
WV0635 # 08 Y:2022 | 08 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $949 | $525 | Implemented |
WV0635 # 10 Y:2022 | 10 | 2022 | DEVELOP A REPAIR/REPLACE POLICY | $546 | $1,571 | Implemented |
WV0635 # 05 Y:2022 | 05 | 2022 | INSTALL SET-BACK TIMERS | $3,167 | $1,125 | Not Implemented |
WV0635 # 07 Y:2022 | 07 | 2022 | USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE | $2,027 | $394 | Implemented |
WV0635 # 09 Y:2022 | 09 | 2022 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $672 | $1,500 | Implemented |
WV0576 # 06 Y:2019 | 06 | 2019 | DEVELOP A REPAIR/REPLACE POLICY | $10,175 | $833 | Implemented |
WV0576 # 05 Y:2019 | 05 | 2019 | RECYCLE WHITE WATER | $10,243 | $11,900 | Not Implemented |
WV0576 # 04 Y:2019 | 04 | 2019 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $13,307 | $1,000 | Implemented |
WV0576 # 03 Y:2019 | 03 | 2019 | UPGRADE CONTROLS ON COMPRESSORS | $51,831 | $25,750 | Not Implemented |
WV0576 # 07 Y:2019 | 07 | 2019 | INSTALL OCCUPANCY SENSORS | $5,850 | $2,860 | Implemented |
WV0576 # 08 Y:2019 | 08 | 2019 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $5,463 | $0 | Not Implemented |
WV0576 # 02 Y:2019 | 02 | 2019 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $141,742 | $375,000 | Not Implemented |
WV0576 # 01 Y:2019 | 01 | 2019 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $274,752 | $432,000 | Not Implemented |
WV0576 # 09 Y:2019 | 09 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,759 | $2,875 | Implemented |
WV0418 # 13 Y:2010 | 13 | 2010 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,837 | $3,870 | Not Implemented |
WV0418 # 12 Y:2010 | 12 | 2010 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $9,456 | $5,095 | Implemented |
WV0418 # 11 Y:2010 | 11 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,872 | $35,956 | Implemented |
WV0418 # 06 Y:2010 | 06 | 2010 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $33,207 | $16,040 | Not Implemented |
WV0418 # 05 Y:2010 | 05 | 2010 | USE WASTE HEAT FROM FLUE GASES TO HEAT SPACE CONDITIONING AIR | $35,021 | $47,775 | Not Implemented |