IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

33

matching recommendations
Reset
NAICS 3279 Other Nonmetallic Mineral Product Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SF0367 # 05 Y:2008 05 2008 INSTALL TIMERS AND/OR THERMOSTATS $1,679 $143 Implemented
SF0367 # 06 Y:2008 06 2008 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $14,633 $1,078 Implemented
SF0367 # 09 Y:2008 09 2008 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $11,030 $7,537 Implemented
SF0367 # 01 Y:2008 01 2008 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $169,502 $10,920 Implemented
SF0367 # 07 Y:2008 07 2008 INSTALL OCCUPANCY SENSORS $9,914 $1,497 Implemented
SF0367 # 11 Y:2008 11 2008 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $14,022 $18,000 Implemented
SF0367 # 02 Y:2008 02 2008 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $121,210 $720 Implemented
SF0367 # 08 Y:2008 08 2008 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $21,234 $9,745 Implemented
SF0367 # 03 Y:2008 03 2008 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $16,340 $5,460 Implemented
SF0367 # 04 Y:2008 04 2008 TURN OFF EQUIPMENT WHEN NOT IN USE $360 $0 Implemented
SF0367 # 10 Y:2008 10 2008 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $7,802 $10,433 Implemented
SF0367 # 12 Y:2008 12 2008 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $5,318 $11,290 Implemented
MS0332 # 06 Y:2008 06 2008 USE OPTIMUM THICKNESS INSULATION $143 $108 Implemented
MS0332 # 05 Y:2008 05 2008 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $14,696 $6,360 Implemented
MS0332 # 01 Y:2008 01 2008 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $771,322 $1,000 Implemented
MS0332 # 02 Y:2008 02 2008 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $358,713 $96,000 Not Implemented
MS0332 # 03 Y:2008 03 2008 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $29,875 $65,823 Implemented
MS0332 # 04 Y:2008 04 2008 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $11,591 $401 Implemented
UD0777 # 14 Y:2008 14 2008 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,509 $3,815 Implemented
UD0777 # 13 Y:2008 13 2008 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY $4,240 $0 Implemented
UD0777 # 12 Y:2008 12 2008 COOL COMPRESSOR AIR INTAKE WITH HEAT EXCHANGER $8,318 $19,000 Implemented
UD0777 # 11 Y:2008 11 2008 USE MINIMUM STEAM OPERATING PRESSURE $7,900 $0 Not Implemented
UD0777 # 08 Y:2008 08 2008 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $33,252 $1,000 Implemented
UD0777 # 06 Y:2008 06 2008 INSTALL DE-AERATOR IN PLACE OF CONDENSATE TANK $35,664 $50,000 Implemented
UD0777 # 05 Y:2008 05 2008 REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER $45,421 $74,873 Not Implemented