IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

66

matching recommendations
Reset
NAICS 331 Primary Metal Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
IA0524 # 01 Y:2014 01 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,605 $3,229 Implemented
IA0524 # 02 Y:2014 02 2014 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,592 $197 Implemented
IA0524 # 03 Y:2014 03 2014 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $620 $89 Implemented
IA0524 # 04 Y:2014 04 2014 INSTALL OCCUPANCY SENSORS $369 $1,010 Not Implemented
IA0524 # 05 Y:2014 05 2014 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $297 $35 Implemented
IA0524 # 06 Y:2014 06 2014 USE OPTIMUM TEMPERATURE $660 $20 Implemented
IA0524 # 07 Y:2014 07 2014 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $408 $110 Implemented
IA0521 # 04 Y:2014 04 2014 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $41,190 $3,600 Not Implemented
IA0521 # 01 Y:2014 01 2014 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY $116,438 $25,000 Implemented
IA0521 # 03 Y:2014 03 2014 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY $4,593 $1,750 Implemented
IA0521 # 07 Y:2014 07 2014 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $3,616 $2,313 Implemented
IA0521 # 02 Y:2014 02 2014 INSULATE BARE EQUIPMENT $7,861 $500 Implemented
IA0521 # 05 Y:2014 05 2014 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $6,258 $355 Not Implemented
IA0521 # 06 Y:2014 06 2014 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,158 $70 Implemented
IA0521 # 08 Y:2014 08 2014 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $1,689 $350 Not Implemented
IA0489 # 08 Y:2012 08 2012 REDUCE VENTILATION AIR $5,734 $1,725 Implemented
IA0489 # 07 Y:2012 07 2012 OPTIMIZE PLANT POWER FACTOR $8,468 $3,237 Not Implemented
IA0489 # 06 Y:2012 06 2012 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $4,423 $1,091 Implemented
IA0489 # 05 Y:2012 05 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,029 $532 Implemented
IA0489 # 04 Y:2012 04 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $9,978 $13,325 Implemented
IA0489 # 03 Y:2012 03 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,582 $12,659 Implemented
IA0489 # 02 Y:2012 02 2012 INSTALL OCCUPANCY SENSORS $336 $298 Implemented
IA0489 # 01 Y:2012 01 2012 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $1,668 $385 Not Implemented
IA0432 # 08 Y:2008 08 2008 RECOVER WASTE HEAT FROM EQUIPMENT $16,295 $3,442 Not Implemented
IA0432 # 10 Y:2008 10 2008 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,529 $1,781 Not Implemented