Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
342
matching recommendationsNAICS | 33121 | Iron and Steel Pipe and Tube Manufacturing from Purchased Steel |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0813 # 10 Y:2011 | 10 | 2011 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $19,937 | $8,250 | Not Implemented |
OK0813 # 11 Y:2011 | 11 | 2011 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $8,447 | $25,472 | Implemented |
TT0051 # 01 Y:2010 | 01 | 2010 | OPTIMIZE PLANT POWER FACTOR | $30,200 | $50,000 | Not Implemented |
TT0051 # 02 Y:2010 | 02 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,895 | $4,900 | Not Implemented |
TT0051 # 03 Y:2010 | 03 | 2010 | INSTALL OCCUPANCY SENSORS | $8,500 | $15,750 | Not Implemented |
TT0051 # 04 Y:2010 | 04 | 2010 | INSTALL OCCUPANCY SENSORS | $1,300 | $2,800 | Not Implemented |
DL0041 # 01 Y:2009 | 01 | 2009 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $29,782 | $0 | Not Implemented |
DL0041 # 02 Y:2009 | 02 | 2009 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $20,570 | $372 | Not Implemented |
DL0041 # 03 Y:2009 | 03 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,474 | $10,800 | Implemented |
DL0041 # 04 Y:2009 | 04 | 2009 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,029 | $1,430 | Implemented |
DL0041 # 05 Y:2009 | 05 | 2009 | INSTALL / REPAIR INSULATION ON STEAM LINES | $3,520 | $400 | Implemented |
DL0041 # 06 Y:2009 | 06 | 2009 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $3,714 | $1,000 | Not Implemented |
DL0041 # 07 Y:2009 | 07 | 2009 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,000 | $348 | Implemented |
DL0041 # 08 Y:2009 | 08 | 2009 | REDUCE VENTILATION AIR | $5,400 | $6,300 | Not Implemented |
DL0041 # 09 Y:2009 | 09 | 2009 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,779 | $3,858 | Implemented |
MS0337 # 01 Y:2009 | 01 | 2009 | COVER OPEN TANKS | $284,008 | $8,869 | Implemented |
MS0337 # 02 Y:2009 | 02 | 2009 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $43,299 | $6,450 | Not Implemented |
MS0337 # 03 Y:2009 | 03 | 2009 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $38,691 | $2,000 | Not Implemented |
MS0337 # 04 Y:2009 | 04 | 2009 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,045 | $5,142 | Not Implemented |
MS0337 # 05 Y:2009 | 05 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,874 | $4,735 | Not Implemented |
SD0411 # 01 Y:2008 | 01 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,081 | $28,585 | Not Implemented |
SD0411 # 02 Y:2008 | 02 | 2008 | USE PHOTOCELL CONTROLS | $5,157 | $4,950 | Not Implemented |
SD0411 # 03 Y:2008 | 03 | 2008 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,238 | $2,428 | Not Implemented |
SD0411 # 04 Y:2008 | 04 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,111 | $6,578 | Not Implemented |
SD0411 # 05 Y:2008 | 05 | 2008 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,030 | $3,394 | Not Implemented |