Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
594
matching recommendationsNAICS | 3314 | Nonferrous Metal (except Aluminum) Production and Processing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0639 # 01 Y:2023 | 01 | 2023 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $1,281,087 | $1,151,450 | Not Implemented |
SF0584 # 06 Y:2022 | 06 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $123,728 | $381,839 | Not Implemented |
SF0584 # 05 Y:2022 | 05 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $6,260 | $23,959 | Not Implemented |
SF0584 # 04 Y:2022 | 04 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,188 | $24,576 | Not Implemented |
SF0584 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,882 | $13,939 | Implemented |
SF0584 # 02 Y:2022 | 02 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,093 | $4,749 | Not Implemented |
SF0584 # 01 Y:2022 | 01 | 2022 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $9,346 | $2,177 | Implemented |
IC0259 # 04 Y:2022 | 04 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,393 | $953 | Not Implemented |
IC0259 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,107 | $15,295 | Not Implemented |
IC0259 # 02 Y:2022 | 02 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $9,350 | $730 | Not Implemented |
IC0259 # 01 Y:2022 | 01 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $914 | $50 | Not Implemented |
TT0265 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,587 | $3,967 | Implemented |
TT0265 # 02 Y:2022 | 02 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,704 | $9,000 | Not Implemented |
TT0265 # 01 Y:2022 | 01 | 2022 | INSULATE BARE EQUIPMENT | $12,477 | $2,065 | Not Implemented |
MA0827 # 01 Y:2021 | 01 | 2021 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $32,062 | $75,000 | Not Implemented |
MA0827 # 02 Y:2021 | 02 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $18,909 | $26,950 | Implemented |
MA0827 # 03 Y:2021 | 03 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,022 | $11,050 | Not Implemented |
MA0827 # 04 Y:2021 | 04 | 2021 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $5,685 | $2,000 | Implemented |
MA0827 # 05 Y:2021 | 05 | 2021 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $2,962 | $10,800 | Not Implemented |
MA0827 # 06 Y:2021 | 06 | 2021 | MINIMIZE WATER USAGE | $1,374 | $3,230 | Not Implemented |
MA0827 # 07 Y:2021 | 07 | 2021 | INSULATE BARE EQUIPMENT | $801 | $1,550 | Not Implemented |
LS2008 # 01 Y:2020 | 01 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $255 | $25 | Implemented |
LS2008 # 02 Y:2020 | 02 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,491 | $1,125 | Implemented |
LS2008 # 03 Y:2020 | 03 | 2020 | INSTALL OCCUPANCY SENSORS | $188 | $50 | Not Implemented |
LS2008 # 04 Y:2020 | 04 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,024 | $8,534 | Implemented |